  "schema_version": 3,
  "generated_on": "2026-09-26",
  "title": "Epoch AI site connection research targets",
  "purpose": "One research target record for every canonical Epoch AI site, preserving its best-known grid/connection jurisdiction, current site-specific match state, sources to search next, and map geometry.",
  "accounting": "These are research-target records, not claims of verified queue membership. A jurisdiction mapping is not a site-specific queue match. Coordinates are display geometry copied from the canonical Epoch map record and retain its precision label.",
  "record_count": 93,
  "records": [
    {
      "epoch_id": "EPOCH-c20399471d1c5e4a",
      "epoch_name": "Colossus 2",
      "country": "United States",
      "state_province": "TN",
      "address": "5420 Tulane Rd, Memphis, TN 38109",
      "current_it_power_mw": 946,
      "current_h100_equivalents": 1111672.5618999496,
      "grid_or_queue_jurisdiction": "TVA / Tennessee transmission providers",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/tn/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TN is assigned to the TVA / Tennessee transmission providers queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 35.8,
      "lon": -86.3,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_power_request",
          "authority": "Tennessee Valley Authority (TVA)",
          "record_name": "Colossus II direct-supply power request",
          "source_url": "https://dailymemphian.com/article/65680/spacexai-power-memphis-tennessee-valley-authority-tva",
          "source_kind": "dated local reporting on utility request",
          "confidence": "medium",
          "basis": "The August 20, 2026 report states that SpaceXAI asked TVA to directly supply more electricity to its Colossus II campus spanning Memphis and Southaven. This establishes a site-specific TVA power relationship/request, not a queue ID."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "SpaceXAI #confident / Anthropic #confident, Cursor #confident, SpaceXAI #confident",
      "utility_or_service_provider": "Tennessee Valley Authority (TVA)",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-d9050b43689ed24c",
      "epoch_name": "Microsoft Fairwater Atlanta",
      "country": "United States",
      "state_province": "GA",
      "address": "1435 Hwy 54 W, Fayetteville, GA 30214",
      "current_it_power_mw": 636,
      "current_h100_equivalents": 768768.7220818596,
      "grid_or_queue_jurisdiction": "SERC / Georgia transmission providers",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/ga/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State GA is assigned to the SERC / Georgia transmission providers queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 32.7,
      "lon": -83.4,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Georgia Power",
          "record_name": "Fairwater Atlanta utility relationship",
          "source_url": "https://registry.deploy.report/datacenters/facilities/qts-fayetteville-ga-campus",
          "source_kind": "secondary sourced facility registry",
          "confidence": "medium",
          "basis": "The facility record identifies Georgia Power as the utility and describes the Ashley Park 500/230-kV substation and customer substations serving the Fayetteville campus. This is utility/site evidence, not a site-specific queue ID."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Microsoft #confident / OpenAI #likely, Microsoft #likely",
      "utility_or_service_provider": "Georgia Power",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-45b3c74314eb1f26",
      "epoch_name": "Anthropic-Amazon New Carlisle",
      "country": "United States",
      "state_province": "IN",
      "address": "55001 Larrison Blvd, New Carlisle, IN 46552",
      "current_it_power_mw": 910,
      "current_h100_equivalents": 685912.076806468,
      "grid_or_queue_jurisdiction": "MISO",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.misoenergy.org/api/giqueue/getprojects",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State IN is assigned to the MISO queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 39.9,
      "lon": -86.3,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Indiana Michigan Power (AEP)",
          "record_name": "Project Rainier / New Carlisle power supply",
          "source_url": "https://www.compute-atlas.com/facilities/amazon-project-rainier-new-carlisle-in",
          "source_kind": "secondary sourced facility registry",
          "confidence": "medium",
          "basis": "The facility record identifies grid power from Indiana Michigan Power together with natural-gas generation for the Amazon Project Rainier campus in New Carlisle. This is site-level utility evidence, not a formal queue ID."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Amazon #confident / Anthropic #confident",
      "utility_or_service_provider": "Indiana Michigan Power (AEP)",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-ea699c935d46e066",
      "epoch_name": "Google Pryor (North)",
      "country": "United States",
      "state_province": "OK",
      "address": "4581 Webb St, Pryor, OK 74361",
      "current_it_power_mw": 368,
      "current_h100_equivalents": 636685.1945426983,
      "grid_or_queue_jurisdiction": "SPP",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://opsportal.spp.org/Studies/GIActive",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State OK is assigned to the SPP queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 35.6,
      "lon": -97.5,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Grand River Dam Authority (GRDA)",
          "record_name": "Google Pryor power supply / customer relationship",
          "source_url": "https://grda.com/wp-content/uploads/2025/06/Continuing-Disclosure-2024_06.26.2025-FINAL.pdf",
          "source_kind": "official GRDA continuing-disclosure document",
          "confidence": "medium",
          "basis": "GRDA's official continuing-disclosure filing identifies Google Inc. as a major industrial/commercial power customer. Combined with the Epoch Pryor site identity, this establishes a public utility/customer relationship but not a site-specific interconnection case."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google #confident / Google DeepMind #speculative",
      "utility_or_service_provider": "Grand River Dam Authority (GRDA)",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-8838deed95ffb554",
      "epoch_name": "Meta Prometheus",
      "country": "United States",
      "state_province": "OH",
      "address": "1 Community Cir, New Albany, OH 43054",
      "current_it_power_mw": 496,
      "current_h100_equivalents": 599845.17433047,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State OH is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 40.4,
      "lon": -82.8,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 2,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_capacity_record",
          "authority": "AEP Ohio",
          "record_name": "Meta Prometheus public utility/facility record",
          "source_url": "https://www.datacenter.fyi/utility/american-electric-power",
          "source_kind": "public-record facility index",
          "confidence": "medium",
          "capacity_mw": 695,
          "capacity_kind": "reported facility capacity",
          "basis": "The AEP public-record index lists Meta Prometheus in Ohio and associates it with AEP; a reported 695 MW facility capacity is retained as source-specific facility data, not equated with queue capacity or measured load."
        },
        {
          "type": "site_specific_utility_relationship",
          "authority": "AEP Ohio",
          "record_name": "Meta Prometheus grid relationship",
          "source_url": "https://registry.deploy.report/datacenters/facilities/meta-ohio-new-albany",
          "source_kind": "secondary sourced facility registry",
          "confidence": "medium",
          "basis": "The facility record identifies AEP Ohio as the grid-interconnection utility for the Meta New Albany campus. The record is retained as corroborating utility evidence."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta #confident / Meta #confident",
      "utility_or_service_provider": "AEP Ohio",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-2c2e40ddb178da3e",
      "epoch_name": "OpenAI Stargate Abilene",
      "country": "United States",
      "state_province": "TX",
      "address": "5502 Spinks Rd, Abilene, TX 79601",
      "current_it_power_mw": 421,
      "current_h100_equivalents": 509348.15563415864,
      "grid_or_queue_jurisdiction": "ERCOT",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.ercot.com/services/rq/large-load-integration",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TX is assigned to the ERCOT queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 31.1,
      "lon": -99.4,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "AEP Texas / Oncor",
          "record_name": "Stargate Abilene serving-utility record",
          "source_url": "https://registry.deploy.report/datacenters/stargate-infrastructure-stargate-abilene",
          "source_kind": "secondary sourced facility registry",
          "confidence": "medium",
          "basis": "The facility record identifies ERCOT as the grid operator and Oncor / AEP Texas as the serving utility for the Stargate Abilene campus. It also distinguishes grid connection from behind-the-meter generation. This is not a formal queue ID."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Oracle #confident / OpenAI #confident",
      "utility_or_service_provider": "AEP Texas / Oncor",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-f5dc9d7a3f02c2e9",
      "epoch_name": "Microsoft Fairwater Wisconsin",
      "country": "United States",
      "state_province": "WI",
      "address": "4800 90th St, Mount Pleasant, WI 53403",
      "current_it_power_mw": 369,
      "current_h100_equivalents": 445679.63617988885,
      "grid_or_queue_jurisdiction": "MISO",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.misoenergy.org/api/giqueue/getprojects",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State WI is assigned to the MISO queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 44.6,
      "lon": -89.8,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "We Energies",
          "record_name": "Fairwater Mount Pleasant utility relationship",
          "source_url": "https://registry.deploy.report/datacenters/microsoft-fairwater-wisconsin",
          "source_kind": "secondary sourced facility registry",
          "confidence": "medium",
          "basis": "The facility record identifies We Energies as the sole grid power supplier for Microsoft's Fairwater campus and identifies MISO as the grid operator. This is site-level utility evidence, not a queue ID."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Microsoft #confident / OpenAI #likely, Microsoft #likely",
      "utility_or_service_provider": "We Energies",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-04f65e1aee6c98ab",
      "epoch_name": "DayOne Kempas",
      "country": "Malaysia",
      "state_province": "",
      "address": "HP79+MP, 81300 Johor Bahru, Johor, Malaysia",
      "current_it_power_mw": 322.470096,
      "current_h100_equivalents": 367547.2460838808,
      "grid_or_queue_jurisdiction": "Malaysia national / utility grid connection process",
      "scope": "outside_registry_geography",
      "status": "country_connection_system_mapped",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": null,
      "source_type": "country-level connection system",
      "source_date": "2026-09-26",
      "next_research_sources": "TNB grid/service records",
      "match_basis": "Epoch site is outside the current U.S./Canada nine-market registry geography; a national/utility connection system is recorded as the relevant external jurisdiction.",
      "confidence": "jurisdiction",
      "next_action": "Search the named national/transmission/distribution connection system plus regulator and utility records for a site-specific connection record.",
      "lat": 4.2105,
      "lon": 101.9758,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_energy_supply_relationship",
          "authority": "Tenaga Nasional Berhad (TNB)",
          "record_name": "DayOne Johor data-center electricity partnership / CRESS supply",
          "source_url": "https://dayonedc.com/sustainability/dayone-data-centers-partners-with-tnb-to-foster-digital-economy-and-sustainable-development",
          "source_kind": "operator official disclosure",
          "confidence": "high",
          "basis": "DayOne states that it signed an Electricity Supply Agreement with TNB for its Nusajaya Tech Park Phase 1 and describes the strategic partnership for reliable electricity supply to its Johor data-center campus; the operator also identifies Kempas as one of the Johor campuses. This supports TNB as a site/campus energy relationship, not a site-specific queue ID."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "DayOne",
      "utility_or_service_provider": "Tenaga Nasional Berhad (TNB)",
      "utility_type": "national electricity utility",
      "transmission_interconnection_provider": "Malaysia national / utility grid system",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 322.47,
      "public_record_status": "Operational; country/grid connection system mapped; no public site-specific connection case found",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": "2026-09-27",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 5,
        "unpopulated_detailed_fields": 11,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "transmission_interconnection_provider",
          "site_planned_mw",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-d8b28fdbc55817f9",
      "epoch_name": "Google Columbus",
      "country": "United States",
      "state_province": "OH",
      "address": "5076 S High St, Columbus, OH 43207",
      "current_it_power_mw": 303,
      "current_h100_equivalents": 331985.85144012125,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State OH is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 40.4,
      "lon": -82.8,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "AEP Ohio",
          "record_name": "Google Columbus utility relationship",
          "source_url": "https://datacentersexposed.com/facilities/google-columbus",
          "source_kind": "public-source facility registry",
          "confidence": "medium",
          "basis": "The facility record identifies Google Columbus at 5076 S High Street in Columbus, Ohio and associates it with AEP Ohio and PJM. This is a facility/utility relationship, not a queue ID."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google #confident / Google DeepMind #speculative",
      "utility_or_service_provider": "AEP Ohio",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-5b353d56a567a70b",
      "epoch_name": "Google New Albany",
      "country": "United States",
      "state_province": "OH",
      "address": "1101 Beech Rd SW, New Albany, OH 43054",
      "current_it_power_mw": 333,
      "current_h100_equivalents": 323900.9600808489,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State OH is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 40.4,
      "lon": -82.8,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_facility_record",
          "authority": "City of New Albany, Ohio",
          "record_name": "Google New Albany data center",
          "source_url": "https://datacenters.newalbanyohio.org/",
          "source_kind": "municipal data-center information portal",
          "confidence": "high",
          "basis": "City portal identifies Google's New Albany campus as an operating data-center site; utility/queue identity still requires a separate site-level service or queue record."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google #confident / Google DeepMind #speculative",
      "utility_or_service_provider": "City of New Albany, Ohio",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-83ca909f7eb211c7",
      "epoch_name": "Google Mesa",
      "country": "United States",
      "state_province": "AZ",
      "address": null,
      "current_it_power_mw": 183,
      "current_h100_equivalents": 289540.17180394137,
      "grid_or_queue_jurisdiction": "WECC / Arizona serving utilities (APS / SRP)",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/az/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State AZ is assigned to the WECC / Arizona serving utilities (APS / SRP) queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 39.8,
      "lon": -98.6,
      "precision": "country centroid",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 2,
      "site_level_evidence": [
        {
          "type": "site_specific_grid_facility_record",
          "authority": "Arizona Public Service",
          "record_name": "Google Mesa data-center facility record",
          "source_url": "https://www.datacenter.fyi/public-record/google-aa4275ee",
          "source_kind": "public-record facility registry",
          "confidence": "medium",
          "capacity_mw": 275.991,
          "capacity_kind": "facility power capacity",
          "basis": "The public-record facility entry identifies a Google hyperscale site at 7232 E Elliot Rd, Mesa, Arizona, with Arizona Public Service as grid operator and a reported 275.991 MW power capacity. This is a facility/grid record and is not asserted as an APS measured load series."
        },
        {
          "type": "site_specific_utility_relationship",
          "authority": "Arizona Public Service",
          "record_name": "Google Mesa utility relationship",
          "source_url": "https://www.datacenter.fyi/public-record/google-aa4275ee",
          "source_kind": "public-record facility registry",
          "confidence": "medium",
          "capacity_mw": 275.991,
          "capacity_kind": "facility power capacity",
          "basis": "The public-record Google Mesa entry identifies Arizona Public Service as grid operator and reports 275.991 MW of facility power capacity. This is site-level utility/facility evidence, not an APS measured load series or queue ID."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google #confident",
      "utility_or_service_provider": "Arizona Public Service",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-55d4b5e818b5bb2a",
      "epoch_name": "DayOne Nusajaya",
      "country": "Malaysia",
      "state_province": "",
      "address": null,
      "current_it_power_mw": 240,
      "current_h100_equivalents": 281670.4396159676,
      "grid_or_queue_jurisdiction": "Malaysia national / utility grid connection process",
      "scope": "outside_registry_geography",
      "status": "country_connection_system_mapped",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": null,
      "source_type": "country-level connection system",
      "source_date": "2026-09-26",
      "next_research_sources": "TNB grid/service records",
      "match_basis": "Epoch site is outside the current U.S./Canada nine-market registry geography; a national/utility connection system is recorded as the relevant external jurisdiction.",
      "confidence": "jurisdiction",
      "next_action": "Search the named national/transmission/distribution connection system plus regulator and utility records for a site-specific connection record.",
      "lat": 4.2105,
      "lon": 101.9758,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_energy_supply_relationship",
          "authority": "Tenaga Nasional Berhad (TNB)",
          "record_name": "DayOne Nusajaya Tech Park Phase 1 Electricity Supply Agreement",
          "source_url": "https://dayonedc.com/sustainability/dayone-data-centers-partners-with-tnb-to-foster-digital-economy-and-sustainable-development",
          "source_kind": "operator official disclosure",
          "confidence": "high",
          "basis": "DayOne states that its Electricity Supply Agreement with TNB provides interim 16MW and permanent 85.5MW supply for Nusajaya Tech Park Phase 1 in Johor Bahru. This is phase-specific service evidence, not a campus-wide queue ID."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "DayOne",
      "utility_or_service_provider": "Tenaga Nasional Berhad (TNB)",
      "utility_type": "national electricity utility",
      "transmission_interconnection_provider": "Malaysia national / utility grid system",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 240,
      "public_record_status": "Operational; no public site-specific connection case found",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": "2026-09-27",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 5,
        "unpopulated_detailed_fields": 11,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "transmission_interconnection_provider",
          "site_planned_mw",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-2dadeb4b013bef05",
      "epoch_name": "Colossus 1",
      "country": "United States",
      "state_province": "TN",
      "address": "3231 Riverport Rd, Memphis, TN 38109",
      "current_it_power_mw": 340,
      "current_h100_equivalents": 275795.85649317835,
      "grid_or_queue_jurisdiction": "TVA / Tennessee transmission providers",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/tn/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TN is assigned to the TVA / Tennessee transmission providers queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 35.8,
      "lon": -86.3,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_power",
          "authority": "Memphis Light, Gas and Water / TVA",
          "record_name": "Colossus 1 grid supply",
          "source_url": "https://www.mlgw.com/xai",
          "source_kind": "official utility source",
          "confidence": "high",
          "basis": "MLGW maintains a dedicated xAI/Colossus power-information page; independent public reporting and utility references describe the Colossus 1 site as served by the MLGW/TVA system. This establishes the site's utility connection relationship, not a claim about measured continuous load."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "SpaceXAI #confident / Anthropic #confident",
      "utility_or_service_provider": "Memphis Light, Gas and Water / TVA",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-1c8ee8b0305c6313",
      "epoch_name": "Google Council Bluffs (East)",
      "country": "United States",
      "state_province": "IA",
      "address": "10410 Bunge Ave, Council Bluffs, IA 51503",
      "current_it_power_mw": 237,
      "current_h100_equivalents": 255684.68923698837,
      "grid_or_queue_jurisdiction": "MISO",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.misoenergy.org/api/giqueue/getprojects",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State IA is assigned to the MISO queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 42.1,
      "lon": -93.5,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_facility_utility_relationship",
          "authority": "MidAmerican Energy",
          "record_name": "Google Council Bluffs utility relationship",
          "source_url": "https://suedatacenters.org/data-centers/google-council-bluffs-ia",
          "source_kind": "secondary public-record facility registry",
          "confidence": "medium",
          "basis": "The facility registry identifies MidAmerican Energy as the utility for Google's Council Bluffs campus and provides a site-specific facility record. The evidence establishes the utility relationship but does not identify a queue case number."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google #confident / Google DeepMind #speculative",
      "utility_or_service_provider": "MidAmerican Energy",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-ac1ca1cf8df13b3c",
      "epoch_name": "CoreWeave Denton TX",
      "country": "United States",
      "state_province": "TX",
      "address": "8171 Jim Christal Rd, Denton, TX 76207",
      "current_it_power_mw": 262,
      "current_h100_equivalents": 252652.85497726125,
      "grid_or_queue_jurisdiction": "ERCOT",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.ercot.com/services/rq/large-load-integration",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TX is assigned to the ERCOT queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 31.1,
      "lon": -99.4,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_service_contract",
          "authority": "Denton Municipal Electric / Core Scientific",
          "record_name": "Denton Campus power purchase agreement",
          "source_url": "https://investors.corescientific.com/sec-filings/all-sec-filings/content/0001193125-26-165121/d149019dex992.htm",
          "source_kind": "SEC-filed utility/service disclosure",
          "confidence": "high",
          "capacity_mw": 394,
          "capacity_kind": "potential campus load under DME contract",
          "basis": "The SEC filing states that power for the Denton Campus is supplied by Denton Municipal Electric under a power purchase agreement for a total potential campus load of approximately 394 MW, with Core Scientific as the customer. This is a service-contract capacity, not an assertion that 394 MW is continuously consumed."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "CoreWeave #confident / OpenAI #likely",
      "utility_or_service_provider": "Denton Municipal Electric / Core Scientific",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-cc12c3e42b3eaf08",
      "epoch_name": "QTS Richmond 1",
      "country": "United States",
      "state_province": "VA",
      "address": "6000 Technology Blvd, Sandston, VA 23150",
      "current_it_power_mw": 238,
      "current_h100_equivalents": 242546.7407781708,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State VA is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 37.5,
      "lon": -78.7,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 2,
      "site_level_evidence": [
        {
          "type": "site_specific_facility_record",
          "authority": "QTS Data Centers",
          "record_name": "Richmond 1 data-center campus",
          "source_url": "https://q.com/data-centers/richmond-1/",
          "source_kind": "official operator facility disclosure",
          "confidence": "high",
          "capacity_mw": 238,
          "capacity_kind": "QTS campus critical capacity",
          "basis": "QTS identifies Richmond 1 at 6000 Technology Boulevard and related Portugee Road addresses in Sandston, Virginia and states 238 MW campus capacity."
        },
        {
          "type": "site_specific_utility_relationship",
          "authority": "Dominion Energy",
          "record_name": "QTS Richmond 1 utility relationship",
          "source_url": "https://epoch.ai/data/ai-data-centers",
          "source_kind": "Epoch AI site dataset field",
          "confidence": "medium",
          "basis": "The current Epoch AI site record for QTS Richmond 1 lists Dominion Energy in its structured energy-company field. QTS separately identifies the Richmond 1 campus and its 238 MW facility capacity. This is secondary utility-relationship evidence, not a verified PJM queue record or metered load."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "QTS Richmond 1",
      "utility_or_service_provider": "QTS Data Centers",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-8358e445402d91c2",
      "epoch_name": "Meta Rosemount",
      "country": "United States",
      "state_province": "MN",
      "address": "1772-2396 145th St, Rosemount, MN 55068, USA",
      "current_it_power_mw": 178,
      "current_h100_equivalents": 215675.11520970188,
      "grid_or_queue_jurisdiction": "MISO",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.misoenergy.org/api/giqueue/getprojects",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State MN is assigned to the MISO queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 46.3,
      "lon": -94.3,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Xcel Energy",
          "record_name": "Meta Rosemount data-center power supply",
          "source_url": "https://stories.xcelenergy.com/stories/Building-the-21st-century-economy--Xcel-Energy-to-power-new-Meta-data-center",
          "source_kind": "official utility disclosure",
          "confidence": "high",
          "basis": "Xcel Energy's March 15, 2024 announcement states it would provide the energy needed to power Meta's new Rosemount data center and identifies the facility as supporting Meta AI workloads."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta #confident / Meta #confident",
      "utility_or_service_provider": "Xcel Energy",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-0d287943c30fe239",
      "epoch_name": "Amazon Madison Mega Site",
      "country": "United States",
      "state_province": "MS",
      "address": "Amazon Data Services Inc, Madison Mega Site Nissan Parkway and Highway 22 Canton, Mississippi Madison County",
      "current_it_power_mw": 284,
      "current_h100_equivalents": 214348.14354550533,
      "grid_or_queue_jurisdiction": "MISO",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.misoenergy.org/api/giqueue/getprojects",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State MS is assigned to the MISO queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 32.7,
      "lon": -89.7,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_grid_facility_record",
          "authority": "Canton Municipal Utilities",
          "record_name": "Amazon Madison Mega Site public-record entry",
          "source_url": "https://www.datacenter.fyi/state/ms",
          "source_kind": "public-record facility registry",
          "confidence": "medium",
          "capacity_mw": 476.991,
          "capacity_kind": "facility power capacity",
          "basis": "The Mississippi public-record index identifies Amazon Madison Mega Site in the Canton area and associates the Amazon facility record with Canton Municipal Utilities and a reported 476.991 MW capacity. This is facility/service evidence, not a measured consumption series."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Amazon #confident / Anthropic #speculative",
      "utility_or_service_provider": "Canton Municipal Utilities",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-6db3bc2c79843ffd",
      "epoch_name": "Google Bristow",
      "country": "United States",
      "state_province": "VA",
      "address": "13001 Rollins Ford Road, Bristow, VA 20136",
      "current_it_power_mw": 238,
      "current_h100_equivalents": 209860.53562405254,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State VA is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 37.5,
      "lon": -78.7,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 2,
      "site_level_evidence": [
        {
          "type": "site_specific_grid_facility_record",
          "authority": "Dominion Energy Virginia",
          "record_name": "Google Bristow public utility/facility record",
          "source_url": "https://www.datacenter.fyi/state/va/bristow",
          "source_kind": "public-record facility registry",
          "confidence": "medium",
          "capacity_mw": 167.904,
          "capacity_kind": "facility/project capacity reported in public-record index",
          "basis": "The public Bristow facility index associates a Google project with Dominion Energy and reports 167.904 MW; the record is treated as utility/facility evidence rather than a verified transmission queue match."
        },
        {
          "type": "site_specific_utility_relationship",
          "authority": "Dominion Energy Virginia",
          "record_name": "Google Bristow utility relationship",
          "source_url": "https://www.datacenter.fyi/public-record/google-be69857b",
          "source_kind": "public-record facility registry",
          "confidence": "medium",
          "capacity_mw": 167.904,
          "capacity_kind": "facility/project capacity reported in public-record index",
          "basis": "The public-record Google Bristow entry associates the site with Dominion Energy and reports 167.904 MW. This is utility/facility evidence and does not establish a PJM queue ID or measured load."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google / Google DeepMind",
      "utility_or_service_provider": "Dominion Energy Virginia",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-93a4aa4fa40d40ca",
      "epoch_name": "Microsoft Goodyear",
      "country": "United States",
      "state_province": "AZ",
      "address": "14250 W Broadway Rd, Goodyear, AZ 85338",
      "current_it_power_mw": 202,
      "current_h100_equivalents": 205154.11824153614,
      "grid_or_queue_jurisdiction": "WECC / Arizona serving utilities (APS / SRP)",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/az/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State AZ is assigned to the WECC / Arizona serving utilities (APS / SRP) queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 34,
      "lon": -111.9,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 2,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_facility_record",
          "authority": "Arizona Public Service",
          "record_name": "Microsoft Goodyear data-center facility",
          "source_url": "https://suedatacenters.org/data-centers/microsoft-goodyear-az",
          "source_kind": "public-source facility registry",
          "confidence": "medium",
          "basis": "The facility record identifies Microsoft Goodyear in Maricopa County, Arizona and names Arizona Public Service as the utility; it also preserves exact site coordinates. The record reports no established public power-capacity figure for this specific facility, so none is inferred here."
        },
        {
          "type": "site_specific_utility_relationship",
          "authority": "Arizona Public Service",
          "record_name": "Microsoft Goodyear utility relationship",
          "source_url": "https://www.datacenter.fyi/public-record/microsoft-befedf4d",
          "source_kind": "public-record facility registry",
          "confidence": "medium",
          "basis": "The public-record Microsoft Goodyear entry identifies Arizona Public Service as the utility for the site. Facility capacity and actual metered demand remain separate quantities."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Microsoft #confident / OpenAI #likely, Microsoft #confident",
      "utility_or_service_provider": "Arizona Public Service",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-1ac0959562dee191",
      "epoch_name": "Meta Jeffersonville",
      "country": "United States",
      "state_province": "IN",
      "address": "500 8th St, Jeffersonville, IN 47130, USA",
      "current_it_power_mw": 178,
      "current_h100_equivalents": 203132.89540171804,
      "grid_or_queue_jurisdiction": "MISO",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.misoenergy.org/api/giqueue/getprojects",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State IN is assigned to the MISO queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 39.9,
      "lon": -86.3,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Duke Energy Indiana",
          "record_name": "Meta Jeffersonville data-center utility relationship",
          "source_url": "https://datacenters.atmeta.com/wp-content/uploads/2024/10/Indiana-Jeffersonville.pdf",
          "source_kind": "official Meta facility disclosure",
          "confidence": "high",
          "basis": "Meta's Jeffersonville project profile states that Meta is working with Duke Energy as a local partner while building the Jeffersonville data center and pursuing its renewable-energy goals."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta #confident / Meta #confident",
      "utility_or_service_provider": "Duke Energy Indiana",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-6799460068cbed36",
      "epoch_name": "Google Kansas City East",
      "country": "United States",
      "state_province": "MO",
      "address": null,
      "current_it_power_mw": 105,
      "current_h100_equivalents": 202627.5896917635,
      "grid_or_queue_jurisdiction": "SPP",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://opsportal.spp.org/Studies/GIActive",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State MO is assigned to the SPP queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 39.8,
      "lon": -98.6,
      "precision": "country centroid",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_facility_development_record",
          "authority": "Hunt Midwest",
          "record_name": "Google data center at Hunt Midwest Business Center",
          "source_url": "https://huntmidwest.com/2024/03/google-announces-1-billion-data-center-at-hunt-midwest-business-center/",
          "source_kind": "official developer/industrial-park announcement",
          "confidence": "high",
          "basis": "Hunt Midwest publicly announced Google's $1 billion data-center project at the Hunt Midwest Business Center in Kansas City, Missouri. This establishes the project/site relationship; it does not by itself establish an interconnection queue ID or electrical capacity."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google #confident",
      "utility_or_service_provider": "Hunt Midwest",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-bdc85fadae79b6b2",
      "epoch_name": "AWS New Albany",
      "country": "United States",
      "state_province": "OH",
      "address": "13360 Miller Rd NW",
      "current_it_power_mw": 213,
      "current_h100_equivalents": 201111.67256189996,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State OH is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 39.8,
      "lon": -98.6,
      "precision": "country centroid",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_facility_record",
          "authority": "Amazon Web Services",
          "record_name": "AWS New Albany / Beech Road campus",
          "source_url": "https://suedatacenters.org/data-centers/aws-beech-road-new-albany-oh",
          "source_kind": "public-source facility registry",
          "confidence": "medium",
          "basis": "The public facility record identifies the AWS New Albany Beech/Miller Road campus in New Albany, Ohio and provides exact coordinates plus a construction status. It does not establish an electrical service or queue ID, so none is inferred."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Amazon #confident",
      "utility_or_service_provider": "Amazon Web Services",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-4eeccbee73808216",
      "epoch_name": "Google Omaha",
      "country": "United States",
      "state_province": "NE",
      "address": "11110 State St, Omaha, NE 68142",
      "current_it_power_mw": 237,
      "current_h100_equivalents": 198585.14401212733,
      "grid_or_queue_jurisdiction": "SPP",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://opsportal.spp.org/Studies/GIActive",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State NE is assigned to the SPP queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 41.5,
      "lon": -99.8,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 2,
      "site_level_evidence": [
        {
          "type": "site_specific_facility_record",
          "authority": "Google",
          "record_name": "Google Omaha data center",
          "source_url": "https://datacenters.google/locations/nebraska/",
          "source_kind": "official Google location disclosure",
          "confidence": "high",
          "basis": "Google's Nebraska data-center page identifies Omaha as one of Google's Nebraska data-center communities and documents continued data-center investment there."
        },
        {
          "type": "site_specific_utility_relationship",
          "authority": "Omaha Public Power District",
          "record_name": "Google Omaha demand-response / utility relationship",
          "source_url": "https://blog.google/innovation-and-ai/infrastructure-and-cloud/global-network/how-were-making-data-centers-more-flexible-to-benefit-power-grids/",
          "source_kind": "official Google utility-interaction disclosure",
          "confidence": "high",
          "basis": "Google's published data-center grid-flexibility update says Google demonstrated demand response with Omaha Public Power District by reducing power demand associated with machine-learning workloads during three grid events. This establishes a site-specific utility interaction, not a queue ID or interval meter dataset."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google #confident / Google DeepMind #speculative",
      "utility_or_service_provider": "Google",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-e06bc7faa8b1b187",
      "epoch_name": "Google Lincoln",
      "country": "United States",
      "state_province": "NE",
      "address": "5475 Cloud Ct, Lincoln, NE 68514",
      "current_it_power_mw": 141,
      "current_h100_equivalents": 197574.53259221828,
      "grid_or_queue_jurisdiction": "SPP",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://opsportal.spp.org/Studies/GIActive",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State NE is assigned to the SPP queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 41.6,
      "lon": -72.7,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_facility_record",
          "authority": "Google",
          "record_name": "Google Lincoln data center",
          "source_url": "https://datacenters.google/locations/nebraska/",
          "source_kind": "official Google location disclosure",
          "confidence": "high",
          "basis": "Google's Nebraska data-center page identifies Lincoln as a Google data-center location and records that the Lincoln, Nebraska data center came online in 2026."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google #confident",
      "utility_or_service_provider": "Google",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-052be5b551cd099b",
      "epoch_name": "QTS Richmond 2",
      "country": "United States",
      "state_province": "VA",
      "address": "6030–6070 Technology Blvd, Sandston, VA 23150",
      "current_it_power_mw": 180,
      "current_h100_equivalents": 182920.66700353715,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State VA is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 37.5,
      "lon": -78.7,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 2,
      "site_level_evidence": [
        {
          "type": "site_specific_facility_record",
          "authority": "QTS Data Centers",
          "record_name": "Richmond 2 data-center campus",
          "source_url": "https://q.com/data-centers/richmond-2/",
          "source_kind": "official operator facility disclosure",
          "confidence": "high",
          "capacity_mw": 180,
          "capacity_kind": "QTS planned critical campus capacity",
          "basis": "QTS identifies the Richmond 2 campus in Sandston, Virginia and states 180 MW planned upon completion at the named campus."
        },
        {
          "type": "site_specific_utility_relationship",
          "authority": "Dominion Energy",
          "record_name": "QTS Richmond 2 secondary utility relationship",
          "source_url": "https://epoch.ai/data/ai-data-centers",
          "source_kind": "Epoch AI structured site field",
          "confidence": "medium",
          "basis": "The preserved Epoch AI record for QTS Richmond 2 lists Dominion Energy in its structured energy-company field. This is secondary site-level utility evidence; it is not a verified PJM queue ID or measured load series."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "QTS Richmond 2",
      "utility_or_service_provider": "QTS Data Centers",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-40ccef8ef4236635",
      "epoch_name": "Google The Dalles",
      "country": "United States",
      "state_province": "OR",
      "address": "3500 River Rd, The Dalles, OR",
      "current_it_power_mw": 154,
      "current_h100_equivalents": 175341.0813542193,
      "grid_or_queue_jurisdiction": "WECC / BPA and Pacific Northwest utilities",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/or/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State OR is assigned to the WECC / BPA and Pacific Northwest utilities queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 44,
      "lon": -120.5,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Northern Wasco County PUD",
          "record_name": "Google The Dalles serving utility",
          "source_url": "https://registry.deploy.report/datacenters/facilities/google-the-dalles-river-road-building-wasco-or",
          "source_kind": "sourced public facility registry",
          "confidence": "high",
          "basis": "DEPLOY identifies the Google The Dalles facility at 3500 River Road and lists Northern Wasco County PUD as the serving utility and grid source. The record is site-level utility evidence, not a site-specific transmission queue ID or metered load series."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google #confident",
      "utility_or_service_provider": "Northern Wasco County PUD",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-02484a65a5dac16d",
      "epoch_name": "QTS Richmond 3",
      "country": "United States",
      "state_province": "VA",
      "address": "3525–3543 Portugee Rd, Sandston, VA 23150",
      "current_it_power_mw": 144,
      "current_h100_equivalents": 174835.77564426477,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State VA is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 37.5,
      "lon": -78.7,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 2,
      "site_level_evidence": [
        {
          "type": "site_specific_facility_record",
          "authority": "QTS Data Centers",
          "record_name": "Richmond 3 data-center campus",
          "source_url": "https://q.com/data-centers/richmond-3/",
          "source_kind": "official operator facility disclosure",
          "confidence": "high",
          "capacity_mw": 240,
          "capacity_kind": "QTS planned critical campus capacity",
          "basis": "QTS identifies Richmond 3 in Sandston, Virginia and states 240 MW planned upon completion for the 221-acre campus."
        },
        {
          "type": "site_specific_utility_relationship",
          "authority": "Dominion Energy",
          "record_name": "QTS Richmond 3 secondary utility relationship",
          "source_url": "https://epoch.ai/data/ai-data-centers",
          "source_kind": "Epoch AI structured site field",
          "confidence": "medium",
          "basis": "The preserved Epoch AI record for QTS Richmond 3 lists Dominion Energy in its structured energy-company field. This is secondary site-level utility evidence; it is not a verified PJM queue ID or measured load series."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "QTS Richmond 3",
      "utility_or_service_provider": "QTS Data Centers",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-0788d9aeb3114553",
      "epoch_name": "Meta Montgomery",
      "country": "United States",
      "state_province": "AL",
      "address": "Co Rd 42, Montgomery, AL 36105, USA",
      "current_it_power_mw": 153,
      "current_h100_equivalents": 174517.43304699342,
      "grid_or_queue_jurisdiction": "SERC / Alabama transmission providers",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/al/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State AL is assigned to the SERC / Alabama transmission providers queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 32.8,
      "lon": -86.8,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_regulatory",
          "authority": "Alabama Public Service Commission / Alabama Power",
          "record_id": "Docket 32382",
          "record_name": "Dotier participation contract",
          "source_url": "https://www.psc.alabama.gov/",
          "source_kind": "state commission docket reference",
          "confidence": "medium",
          "basis": "The Alabama PSC record concerns an Alabama Power participation contract with Dotier, a Meta subsidiary, supporting projects for the Montgomery-area data center."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta #confident / Meta #confident",
      "utility_or_service_provider": "Alabama Public Service Commission / Alabama Power",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-5de9a1c70a3e2275",
      "epoch_name": "Meta Kuna",
      "country": "United States",
      "state_province": "ID",
      "address": "601 Kuna Mora Rd,  Kuna ID 83634",
      "current_it_power_mw": 152,
      "current_h100_equivalents": 173247.67205659422,
      "grid_or_queue_jurisdiction": "WECC / Idaho Power, PacifiCorp, BPA and Avista",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/id/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State ID is assigned to the WECC / Idaho Power, PacifiCorp, BPA and Avista queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 44.2,
      "lon": -114.6,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Idaho Power",
          "record_name": "Meta Kuna data-center energy planning",
          "source_url": "https://datacenters.atmeta.com/2026/09/kuna-we-are-online/",
          "source_kind": "official Meta facility disclosure",
          "confidence": "high",
          "basis": "Meta states it worked with Idaho Power years in advance to plan for the Kuna data center's energy needs and identifies Idaho Power among the local partners for the operating site."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta #confident / Meta #confident",
      "utility_or_service_provider": "Idaho Power",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-6ff5e1aeb6f0c7e3",
      "epoch_name": "Meta Temple",
      "country": "United States",
      "state_province": "TX",
      "address": "2310 Eberhardt Rd, Temple, TX 76504",
      "current_it_power_mw": 152,
      "current_h100_equivalents": 173247.6719844078,
      "grid_or_queue_jurisdiction": "ERCOT",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.ercot.com/services/rq/large-load-integration",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TX is assigned to the ERCOT queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 31.1,
      "lon": -99.4,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Oncor Electric",
          "record_name": "Meta Temple data-center energy planning",
          "source_url": "https://datacenters.atmeta.com/2026/07/temple-we-are-online/",
          "source_kind": "official Meta facility disclosure",
          "confidence": "high",
          "basis": "Meta states it worked with Oncor Electric years in advance to plan for and meet the Temple data center's energy needs and identifies Oncor among the local project partners."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta #confident / Meta #confident",
      "utility_or_service_provider": "Oncor Electric",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-14cecdb5956daea1",
      "epoch_name": "Meta Cheyenne",
      "country": "United States",
      "state_province": "WY",
      "address": "Cheyenne, WY 82007, USA",
      "current_it_power_mw": 152,
      "current_h100_equivalents": 172814.5528044467,
      "grid_or_queue_jurisdiction": "WECC / Wyoming serving utilities",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/wy/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State WY is assigned to the WECC / Wyoming serving utilities queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 43,
      "lon": -107.6,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Black Hills Energy",
          "record_name": "Meta Cheyenne grid / energy relationship",
          "source_url": "https://datacenters.atmeta.com/2024/07/hello-cheyenne/",
          "source_kind": "official Meta project disclosure",
          "confidence": "high",
          "basis": "Meta's July 2, 2024 first-party Cheyenne project announcement says Meta will work with Black Hills Energy to add new resources to the grid, including renewables. This establishes a site-specific utility/grid relationship, not a queue ID or measured load."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta #confident / Meta #confident",
      "utility_or_service_provider": "Black Hills Energy",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-4a87099a6d1e001f",
      "epoch_name": "Amazon Ridgeland",
      "country": "United States",
      "state_province": "MS",
      "address": "1626 County Line Road Ridgeland, Mississippi",
      "current_it_power_mw": 228,
      "current_h100_equivalents": 171298.6356745831,
      "grid_or_queue_jurisdiction": "MISO",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.misoenergy.org/api/giqueue/getprojects",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State MS is assigned to the MISO queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 32.7,
      "lon": -89.7,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Entergy Mississippi",
          "record_name": "Amazon Ridgeland secondary utility relationship",
          "source_url": "https://epoch.ai/data/ai-data-centers",
          "source_kind": "Epoch AI structured site field",
          "confidence": "medium",
          "basis": "The preserved Epoch AI record for Amazon Ridgeland at 1626 County Line Road, Ridgeland, Mississippi lists Entergy in its structured energy-company field. This is secondary site-level utility evidence and does not establish an interconnection queue ID or metered demand."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Amazon #confident / Anthropic #speculative",
      "utility_or_service_provider": "Entergy Mississippi",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-27e284efc1b1abc2",
      "epoch_name": "Meta Huntsville",
      "country": "United States",
      "state_province": "AL",
      "address": "5400 Prosperity Dr NW, Toney, AL",
      "current_it_power_mw": 146,
      "current_h100_equivalents": 166760.9903991915,
      "grid_or_queue_jurisdiction": "SERC / Alabama transmission providers",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/al/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State AL is assigned to the SERC / Alabama transmission providers queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 32.8,
      "lon": -86.8,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Tennessee Valley Authority",
          "record_name": "Meta Huntsville secondary utility relationship",
          "source_url": "https://epoch.ai/data/ai-data-centers",
          "source_kind": "Epoch AI structured site field",
          "confidence": "medium",
          "basis": "The preserved Epoch AI record for Meta Huntsville in Toney, Alabama lists Tennessee Valley Authority among its structured energy-company fields. This is secondary energy/utility evidence; the other named companies are not assumed to be serving utilities."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta #confident / Meta #confident",
      "utility_or_service_provider": "Tennessee Valley Authority",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-a69e48fd129d0cdb",
      "epoch_name": "Coreweave Helios",
      "country": "United States",
      "state_province": "TX",
      "address": "984 County Road 112, Afton, TX 79220",
      "current_it_power_mw": 132,
      "current_h100_equivalents": 159551.768236855,
      "grid_or_queue_jurisdiction": "ERCOT",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.ercot.com/services/rq/large-load-integration",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TX is assigned to the ERCOT queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 31.1,
      "lon": -99.4,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_SPECIFIC_INTERCONNECTION_AND_SERVICE_EVIDENCE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "CoreWeave / Galaxy Digital",
      "utility_or_service_provider": "AEP Texas Inc.",
      "utility_type": "electric utility / service agreement",
      "transmission_interconnection_provider": "Wind Energy Transmission Texas, LLC (WETT)",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": 830,
      "approved_capacity_mw": 830,
      "contract_ceiling_mw": null,
      "site_planned_mw": 1600,
      "public_record_status": "ERCOT LLIS completed; additional 830 MW approved and utility-contracted; construction underway",
      "request_or_study_date": "2026-01-15",
      "service_or_approval_date": "2026-01-15",
      "target_in_service_date": null,
      "connection_research_notes": "Public source names ERCOT, AEP Texas and WETT and states the additional 830 MW approval; no public ERCOT queue/project identifier was located, so no queue ID is inferred.",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 9,
        "unpopulated_detailed_fields": 7,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "transmission_interconnection_provider",
          "service_capacity_mw",
          "approved_capacity_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "contract_ceiling_mw",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-534376160415dc84",
      "epoch_name": "Microsoft Project Osmium",
      "country": "United States",
      "state_province": "IA",
      "address": "5855 SW Kerry St, Cumming, IA 50061",
      "current_it_power_mw": 190,
      "current_h100_equivalents": 155634.15866599293,
      "grid_or_queue_jurisdiction": "MISO",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.misoenergy.org/api/giqueue/getprojects",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State IA is assigned to the MISO queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 42.1,
      "lon": -93.5,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "MidAmerican Energy",
          "record_name": "Microsoft Project Osmium utility relationship",
          "source_url": "https://www.cleanenergydistricts.org/data-centers-in-iowa-resource-hub",
          "source_kind": "secondary Iowa data-center infrastructure registry",
          "confidence": "medium",
          "capacity_mw": 150,
          "capacity_kind": "facility capacity reported by source",
          "basis": "The Iowa data-center resource identifies Microsoft Project Osmium in Iowa and lists MidAmerican Energy as its utility. The 150 MW figure is source-reported facility information and is not substituted for an interconnection-queue capacity or metered demand."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Microsoft #confident / OpenAI #speculative",
      "utility_or_service_provider": "MidAmerican Energy",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-0bb0b996b7c96beb",
      "epoch_name": "Meta Eagle Mountain",
      "country": "United States",
      "state_province": "UT",
      "address": "1275 N Community Cir, Eagle Mountain, UT 84005",
      "current_it_power_mw": 133,
      "current_h100_equivalents": 151354.21930267813,
      "grid_or_queue_jurisdiction": "WECC / Utah serving utility",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/ut/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State UT is assigned to the WECC / Utah serving utility queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 39.3,
      "lon": -111.7,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Rocky Mountain Power",
          "record_name": "Meta Eagle Mountain grid infrastructure relationship",
          "source_url": "https://datacenters.atmeta.com/2026/09/deepening-our-investment-in-eagle-mountain-utah/",
          "source_kind": "official Meta project disclosure",
          "confidence": "high",
          "basis": "Meta's September 14, 2026 first-party Eagle Mountain update says Meta fully funded new generation and grid infrastructure supporting operations on the Rocky Mountain Power grid. This establishes site-specific grid evidence, not a public queue ID or measured load."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta #confident / Meta #confident",
      "utility_or_service_provider": "Rocky Mountain Power",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-85492d2b8df586a1",
      "epoch_name": "Google Midlothian",
      "country": "United States",
      "state_province": "TX",
      "address": "3250 Railport Parkway, Midlothian, TX 76065",
      "current_it_power_mw": 103,
      "current_h100_equivalents": 143580.85118746842,
      "grid_or_queue_jurisdiction": "ERCOT",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.ercot.com/services/rq/large-load-integration",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TX is assigned to the ERCOT queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 31.1,
      "lon": -99.4,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google / Alamo Mission LLC",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 103,
      "public_record_status": "Operational; site-level regulatory identity confirmed; no public site-specific queue/service record located in reviewed sources",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": "Site identity and operation are public; the reviewed evidence does not establish a unique ERCOT queue ID or direct utility service record. Jurisdiction mapping is not promoted to a site match.",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 2,
        "unpopulated_detailed_fields": 14,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "site_planned_mw",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-2b89e13933a04725",
      "epoch_name": "Google Storey County",
      "country": "United States",
      "state_province": "NV",
      "address": null,
      "current_it_power_mw": 161,
      "current_h100_equivalents": 133906.01313794847,
      "grid_or_queue_jurisdiction": "WECC / Nevada serving utility",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/nv/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State NV is assigned to the WECC / Nevada serving utility queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 39.8,
      "lon": -98.6,
      "precision": "country centroid",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Public Utilities Commission of Nevada / NV Energy",
          "record_name": "Google Storey County energy supply agreement",
          "source_url": "https://puc.nv.gov/uploadedFiles/puc.nv.gov/Content/About/Media_Outreach/NewsletterJuly2024.pdf",
          "source_kind": "state utility regulator filing index",
          "confidence": "high",
          "basis": "The Nevada PUC's July 2024 newsletter lists Docket 24-06014, a joint application by Sierra Pacific Power Company d/b/a NV Energy and Callisto Enterprises LLC for approval of an Energy Supply Agreement. The associated public record identifies Google as the customer for data-center electric service in Storey County. This is regulatory/site-service evidence, not a queue ID or measured load."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google #confident / Google DeepMind #speculative",
      "utility_or_service_provider": "Public Utilities Commission of Nevada / NV Energy",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-f92e98f4b76a9bcd",
      "epoch_name": "Google Lancaster",
      "country": "United States",
      "state_province": "OH",
      "address": "105 Whiley Rd, Lancaster, OH 43130",
      "current_it_power_mw": 137,
      "current_h100_equivalents": 130368.8731682668,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State OH is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 40.4,
      "lon": -82.8,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 137,
      "public_record_status": "Operational site identity documented; no public site-specific queue/service record located",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": "A public facility record exists for the exact Lancaster address, but no conservative PJM queue/service identifier was found.",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 2,
        "unpopulated_detailed_fields": 14,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "site_planned_mw",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-78f8285078416a9e",
      "epoch_name": "Meta-QTS Hillsboro 2",
      "country": "United States",
      "state_province": "OR",
      "address": "4755 NE Huffman St, Hillsboro, OR 97124",
      "current_it_power_mw": 180,
      "current_h100_equivalents": 123839,
      "grid_or_queue_jurisdiction": "WECC / BPA and Pacific Northwest utilities",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/or/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State OR is assigned to the WECC / BPA and Pacific Northwest utilities queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 41.5,
      "lon": -99.8,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Portland General Electric",
          "record_name": "Meta-QTS Hillsboro 2 secondary utility relationship",
          "source_url": "https://epoch.ai/data/ai-data-centers",
          "source_kind": "Epoch AI structured site field",
          "confidence": "medium",
          "basis": "The preserved Epoch AI record for Meta-QTS Hillsboro 2 lists Portland General Electric and Avangrid in its structured energy-company field. This is secondary energy/utility evidence at the site level; the record is not a queue ID and Avangrid is not assumed to be the serving utility."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta #likely / Meta #likely",
      "utility_or_service_provider": "Portland General Electric",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-a2c9f0846296fe65",
      "epoch_name": "Google Waltham Cross",
      "country": "United Kingdom",
      "state_province": "",
      "address": "Land at Maxwell's Farm West, Great Cambridge Road, Cheshunt, EN8 8XH",
      "current_it_power_mw": 88,
      "current_h100_equivalents": 123799.89893885801,
      "grid_or_queue_jurisdiction": "Great Britain NESO + local distribution network connections",
      "scope": "outside_registry_geography",
      "status": "country_connection_system_mapped",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": null,
      "source_type": "national connection queue / contracted connections",
      "source_date": "2026-09-26",
      "next_research_sources": "NESO Connections 360; NESO Connections Registers / TEC Register",
      "match_basis": "Epoch site is outside the current U.S./Canada nine-market registry geography; a national/utility connection system is recorded as the relevant external jurisdiction.",
      "confidence": "jurisdiction",
      "next_action": "Search the named national/transmission/distribution connection system plus regulator and utility records for a site-specific connection record.",
      "lat": 55.3781,
      "lon": -3.436,
      "precision": "country centroid",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "epoch_id": "EPOCH-a2c9f0846296fe65",
          "type": "site_specific_energy_contract",
          "authority": "Shell Energy Europe Limited / Google",
          "record_name": "Google Waltham Cross 24/7 carbon-free energy management agreement",
          "source_url": "https://www.datacenters.google/locations/waltham-cross/",
          "source_kind": "official Google facility disclosure",
          "confidence": "high",
          "basis": "Google's Waltham Cross facility page says Google selected Shell Energy Europe Limited as its 24/7 Carbon-Free Energy Manager in the UK and describes the arrangement as contributing to grid stability and the energy transition. This is energy-contract evidence, not a utility interconnection record."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google #confident / Google DeepMind #speculative",
      "utility_or_service_provider": "Shell Energy Europe Limited / Google",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "country_connection_system_mapped",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-a286a89bd1c1b6e7",
      "epoch_name": "VNET Bayin Ulanqab",
      "country": "China",
      "state_province": "",
      "address": "Bayin, Ulanqab, China",
      "current_it_power_mw": 221,
      "current_h100_equivalents": 122789.28751894896,
      "grid_or_queue_jurisdiction": "China State Grid / provincial grid connection process",
      "scope": "outside_registry_geography",
      "status": "country_connection_system_mapped",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": null,
      "source_type": "national / provincial connection system",
      "source_date": "2026-09-26",
      "next_research_sources": "State Grid / provincial grid",
      "match_basis": "Epoch site is outside the current U.S./Canada nine-market registry geography; a national/utility connection system is recorded as the relevant external jurisdiction.",
      "confidence": "jurisdiction",
      "next_action": "Search the named national/transmission/distribution connection system plus regulator and utility records for a site-specific connection record.",
      "lat": 35.8617,
      "lon": 104.1954,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "VNET",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": "China State Grid / Inner Mongolia provincial grid system",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 221,
      "public_record_status": "Operational; no public site-specific connection case found",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 2,
        "unpopulated_detailed_fields": 14,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "transmission_interconnection_provider",
          "site_planned_mw"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-785d6e4c34607dd4",
      "epoch_name": "Google Arcola",
      "country": "United States",
      "state_province": "VA",
      "address": "42575 Arcola Blvd, Sterling, VA 20166",
      "current_it_power_mw": 77,
      "current_h100_equivalents": 108135.42193026781,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State VA is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 37.5,
      "lon": -78.7,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Dominion Energy",
          "record_name": "Google Arcola serving-utility relationship",
          "source_url": "https://suedatacenters.org/data-centers/google-arcola-loudoun-va",
          "source_kind": "secondary sourced facility registry",
          "confidence": "medium",
          "basis": "The SueDataCenters facility record identifies Dominion Energy as the utility for Google's Arcola data-center site in Loudoun County, Virginia. This establishes site-level utility evidence, not a public queue ID or measured load."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google #confident",
      "utility_or_service_provider": "Dominion Energy",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-f1a2bcdd78478bc2",
      "epoch_name": "Google Red Oak",
      "country": "United States",
      "state_province": "TX",
      "address": "330 Austin Blvd, Red Oak, TX 75154",
      "current_it_power_mw": 77,
      "current_h100_equivalents": 108135.42193026781,
      "grid_or_queue_jurisdiction": "ERCOT",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.ercot.com/services/rq/large-load-integration",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TX is assigned to the ERCOT queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 31.1,
      "lon": -99.4,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google / Alamo Mission LLC",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 77,
      "public_record_status": "Operational; TDLR site/project records confirm facility identity; no public site-specific queue/service record located",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": "The exact TDLR project for the Red Oak facility was reviewed; no utility or ERCOT queue identifier was located in the public record reviewed.",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 2,
        "unpopulated_detailed_fields": 14,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "site_planned_mw",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-4525348d114e3e8e",
      "epoch_name": "Google Papillion",
      "country": "United States",
      "state_province": "NE",
      "address": "14651-15249 Gold Coast Rd 68138 Papillion Nebraska, USA",
      "current_it_power_mw": 237,
      "current_h100_equivalents": 100555.83628094998,
      "grid_or_queue_jurisdiction": "SPP",
      "scope": "within_registry_geography",
      "status": "public_customer_planning_record",
      "site_specific_queue_id": null,
      "site_specific_queue_name": "OPPD Google Papillion large-customer planning",
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.oppd.com/media/316613/neomaha01a-pos-2019.pdf",
      "source_type": "OPPD public planning document",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "OPPD public planning material discusses transmission/distribution improvements, capacity purchases and new generation to meet Google's expected system demand for the Papillion data center.",
      "confidence": "high",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 41.5,
      "lon": -99.8,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_planning",
          "authority": "OPPD",
          "record_name": "Google Papillion large-customer planning",
          "source_url": "https://www.oppd.com/media/316613/neomaha01a-pos-2019.pdf",
          "source_kind": "official utility planning document",
          "confidence": "high",
          "basis": "OPPD planning material discusses transmission/distribution improvements, capacity purchases and new generation to meet Google's expected system demand."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "PUBLIC_CUSTOMER_PLANNING_RECORD",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google #confident / Google DeepMind #speculative",
      "utility_or_service_provider": "OPPD",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "public_customer_planning_record",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 2,
        "unpopulated_detailed_fields": 14,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "site_specific_queue_name"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-d29894d37388a96a",
      "epoch_name": "Meta Gallatin",
      "country": "United States",
      "state_province": "TN",
      "address": "1 Meta Lp, Gallatin, TN 37066",
      "current_it_power_mw": 87,
      "current_h100_equivalents": 99545.22486104093,
      "grid_or_queue_jurisdiction": "TVA / Tennessee transmission providers",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/tn/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TN is assigned to the TVA / Tennessee transmission providers queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 35.8,
      "lon": -86.3,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_SPECIFIC_UTILITY_SERVICE_EVIDENCE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta",
      "utility_or_service_provider": "Tennessee Valley Authority (TVA)",
      "utility_type": "electric utility",
      "transmission_interconnection_provider": "Tennessee Valley Authority (TVA)",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "Operational; Meta announced the Gallatin data center was serving traffic",
      "request_or_study_date": null,
      "service_or_approval_date": "2024-11-14",
      "target_in_service_date": null,
      "connection_research_notes": "TVA serving-utility relationship is established in the public facility registry retained by the project. No public TVA queue ID was found.",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 5,
        "unpopulated_detailed_fields": 11,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "transmission_interconnection_provider",
          "service_or_approval_date",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-02c050b6b554fadd",
      "epoch_name": "Meta Los Lunas",
      "country": "United States",
      "state_province": "NM",
      "address": "4250 Messenger Lp, Los Lunas, NM 87031",
      "current_it_power_mw": 87,
      "current_h100_equivalents": 99545.22486104093,
      "grid_or_queue_jurisdiction": "WECC / PNM and other New Mexico serving utilities",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/nm/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State NM is assigned to the WECC / PNM and other New Mexico serving utilities queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 34.4,
      "lon": -106.1,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Public Service Company of New Mexico (PNM)",
          "record_name": "Meta Los Lunas serving-utility relationship",
          "source_url": "https://registry.deploy.report/datacenters/facilities/meta-new-mexico-los-lunas",
          "source_kind": "secondary sourced facility registry",
          "confidence": "medium",
          "basis": "The DEPLOY facility record identifies Public Service Company of New Mexico (PNM) as the serving utility for Meta Los Lunas and records PNM procurement of renewable energy and hybrid BESS to serve the campus. This is secondary site-level utility evidence, not a queue ID or measured load."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta #confident / Meta #confident",
      "utility_or_service_provider": "Public Service Company of New Mexico (PNM)",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-768183e4de6062d2",
      "epoch_name": "CoreWeave Ellendale ND",
      "country": "United States",
      "state_province": "ND",
      "address": "9685 87th Ave SE, Ellendale, ND 58436",
      "current_it_power_mw": 68,
      "current_h100_equivalents": 93481.55634158666,
      "grid_or_queue_jurisdiction": "MISO",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.misoenergy.org/api/giqueue/getprojects",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State ND is assigned to the MISO queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 47.5,
      "lon": -100.5,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "epoch_id": "EPOCH-768183e4de6062d2",
          "type": "site_specific_compute_tenancy",
          "authority": "CoreWeave / Applied Digital",
          "record_name": "CoreWeave Ellendale Campus 250 MW datacenter leases",
          "source_url": "https://www.sec.gov/Archives/edgar/data/1144879/000164117225013199/form8-k.htm",
          "source_kind": "SEC-filed definitive agreement",
          "confidence": "high",
          "basis": "Applied Digital's May 28, 2025 SEC filing says subsidiaries entered leases with CoreWeave to deliver up to an aggregate 250 MW of infrastructure at the 400 MW Ellendale, North Dakota campus, covering Building 2 (100 MW) and Building 3 (150 MW). This establishes a site-specific compute-tenant/capacity contract, not a utility connection or measured load."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "CoreWeave #confident / OpenAI #speculative",
      "utility_or_service_provider": "CoreWeave / Applied Digital",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-4b5df4f52274f2ba",
      "epoch_name": "Meta Sarpy",
      "country": "United States",
      "state_province": "NE",
      "address": "14436-14998 Fairview Rd, Springfield, NE 68059, USA",
      "current_it_power_mw": 80,
      "current_h100_equivalents": 91965.63921172309,
      "grid_or_queue_jurisdiction": "SPP",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://opsportal.spp.org/Studies/GIActive",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State NE is assigned to the SPP queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 41.5,
      "lon": -99.8,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Omaha Public Power District",
          "record_name": "Meta Sarpy serving-utility relationship",
          "source_url": "https://registry.deploy.report/datacenters/facilities/meta-nebraska-sarpy",
          "source_kind": "secondary sourced facility registry",
          "confidence": "medium",
          "basis": "The DEPLOY facility record identifies Omaha Public Power District as the serving utility for Meta Sarpy in Papillion, Nebraska. This is site-level utility evidence, not a queue ID or measured load."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta #confident / Meta #confident",
      "utility_or_service_provider": "Omaha Public Power District",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-77e196fc5320fd70",
      "epoch_name": "Huawei Horinger",
      "country": "China",
      "state_province": "",
      "address": "Huawei, Horinger, China",
      "current_it_power_mw": 184.3,
      "current_h100_equivalents": 89439.11066195049,
      "grid_or_queue_jurisdiction": "China State Grid / provincial grid connection process",
      "scope": "outside_registry_geography",
      "status": "country_connection_system_mapped",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": null,
      "source_type": "national / provincial connection system",
      "source_date": "2026-09-26",
      "next_research_sources": "State Grid / provincial grid",
      "match_basis": "Epoch site is outside the current U.S./Canada nine-market registry geography; a national/utility connection system is recorded as the relevant external jurisdiction.",
      "confidence": "jurisdiction",
      "next_action": "Search the named national/transmission/distribution connection system plus regulator and utility records for a site-specific connection record.",
      "lat": 35.8617,
      "lon": 104.1954,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Huawei",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": "China State Grid / Inner Mongolia provincial grid system",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 346,
      "public_record_status": "Operational; no public site-specific connection case found",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 2,
        "unpopulated_detailed_fields": 14,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "transmission_interconnection_provider",
          "site_planned_mw"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-2d362a1adb09fddd",
      "epoch_name": "CoreWeave Chester VA",
      "country": "United States",
      "state_province": "VA",
      "address": "1401 Meadowville Technology Parkway, Chester, VA",
      "current_it_power_mw": 82,
      "current_h100_equivalents": 88428.49924204143,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State VA is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 37.5,
      "lon": -78.7,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Dominion Energy",
          "record_name": "Meadowville data center utility / power expansion record",
          "source_url": "https://images1.showcase.com/d2/VAfnIWpgV5AWodMZ5wM7cd_ytrzW59_cgel0ES7Hor0/document.pdf",
          "source_kind": "facility property specification",
          "confidence": "high",
          "basis": "A Meadowville facility specification at the exact 1401 Meadowville Technology Parkway address identifies Dominion Energy as the utility and describes a power-expansion timeline. The document predates the current CoreWeave tenancy; it is retained as site-level utility infrastructure evidence, not a CoreWeave-specific service contract."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "CoreWeave / Chirisa",
      "utility_or_service_provider": "Dominion Energy Virginia",
      "utility_type": "electric utility",
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 82,
      "public_record_status": "Operational site identity documented; no public site-specific PJM queue/service record located",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": "2026-09-27",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 4,
        "unpopulated_detailed_fields": 12,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "site_planned_mw",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-ea5d1ae5837aba5c",
      "epoch_name": "Oracle Batam",
      "country": "Indonesia",
      "state_province": "",
      "address": null,
      "current_it_power_mw": 72,
      "current_h100_equivalents": 84386.05356240526,
      "grid_or_queue_jurisdiction": "PLN grid connection process",
      "scope": "outside_registry_geography",
      "status": "country_connection_system_mapped",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": null,
      "source_type": "national utility connection system",
      "source_date": "2026-09-26",
      "next_research_sources": "PLN",
      "match_basis": "Epoch site is outside the current U.S./Canada nine-market registry geography; a national/utility connection system is recorded as the relevant external jurisdiction.",
      "confidence": "jurisdiction",
      "next_action": "Search the named national/transmission/distribution connection system plus regulator and utility records for a site-specific connection record.",
      "lat": -0.7893,
      "lon": 113.9213,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Oracle",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": "PLN grid connection system",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 72,
      "public_record_status": "Operational; no public site-specific connection case found",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 2,
        "unpopulated_detailed_fields": 14,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "transmission_interconnection_provider",
          "site_planned_mw"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-03aad260b30bfbe1",
      "epoch_name": "AWS Berwick",
      "country": "United States",
      "state_province": "PA",
      "address": "1125 Electron Ave, Berwick, PA 18603",
      "current_it_power_mw": 108,
      "current_h100_equivalents": 81354.21930267812,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State PA is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 40.9,
      "lon": -77.8,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_SPECIFIC_POWER_CONTRACT_EVIDENCE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Amazon / AWS",
      "utility_or_service_provider": "Talen Energy",
      "utility_type": "power-contract counterparty",
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": 1920,
      "site_planned_mw": 960,
      "public_record_status": "Planned campus with public Talen power-agreement capacity ceiling; no public PJM queue ID attached to the site",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": "Talen's revised power agreement is a contractual supply ceiling, not an interconnection queue capacity or measured load. It is retained separately from queue MW.",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 5,
        "unpopulated_detailed_fields": 11,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "contract_ceiling_mw",
          "site_planned_mw",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-eb87487504bda8ed",
      "epoch_name": "CoreWeave Marble NC",
      "country": "United States",
      "state_province": "NC",
      "address": "155 Palmer Ln, Marble, NC 28905",
      "current_it_power_mw": 65,
      "current_h100_equivalents": 78827.6907529055,
      "grid_or_queue_jurisdiction": "SERC / North Carolina transmission providers",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/nc/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State NC is assigned to the SERC / North Carolina transmission providers queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 35.5,
      "lon": -79.4,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_service",
          "authority": "Murphy Electric Power Board / Duke Energy",
          "record_name": "Marble data-center utility supply",
          "capacity_mw": 117,
          "source_url": "https://www.sec.gov/Archives/edgar/data/1839341/000119312526165121/d149019dex992.htm",
          "source_kind": "SEC-filed utility/service disclosure",
          "confidence": "high",
          "basis": "Public filing identifies 35 MW from Murphy EPB and 82 MW from Duke Energy for the Marble campus."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "CoreWeave #confident / OpenAI #speculative",
      "utility_or_service_provider": "Murphy Electric Power Board / Duke Energy",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-7d9b5af0cce16f1c",
      "epoch_name": "Meta Aiken",
      "country": "United States",
      "state_province": "SC",
      "address": "7601 State Hwy 105, Trenton, SC 29847, USA",
      "current_it_power_mw": 69,
      "current_h100_equivalents": 78322.38504295099,
      "grid_or_queue_jurisdiction": "SERC / South Carolina transmission providers",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/sc/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State SC is assigned to the SERC / South Carolina transmission providers queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 33.8,
      "lon": -80.9,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Aiken Electric Cooperative",
          "record_name": "Meta Aiken serving-utility relationship",
          "source_url": "https://suedatacenters.org/data-centers/meta-aiken-county-sc",
          "source_kind": "secondary sourced facility registry",
          "confidence": "medium",
          "basis": "The SueDataCenters record identifies Aiken Electric Cooperative as the utility for Meta's Aiken data center in Graniteville, South Carolina. This is secondary utility evidence, not a queue ID or measured load."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta #confident / Meta #confident",
      "utility_or_service_provider": "Aiken Electric Cooperative",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-af62ae3440fe885a",
      "epoch_name": "Huawei Wuhu",
      "country": "China",
      "state_province": "",
      "address": "Wuhu, China",
      "current_it_power_mw": 157,
      "current_h100_equivalents": 76326.42748863062,
      "grid_or_queue_jurisdiction": "China State Grid / provincial grid connection process",
      "scope": "outside_registry_geography",
      "status": "country_connection_system_mapped",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": null,
      "source_type": "national / provincial connection system",
      "source_date": "2026-09-26",
      "next_research_sources": "State Grid / provincial grid",
      "match_basis": "Epoch site is outside the current U.S./Canada nine-market registry geography; a national/utility connection system is recorded as the relevant external jurisdiction.",
      "confidence": "jurisdiction",
      "next_action": "Search the named national/transmission/distribution connection system plus regulator and utility records for a site-specific connection record.",
      "lat": 35.8617,
      "lon": 104.1954,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Huawei",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": "China State Grid / Anhui provincial grid system",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 157,
      "public_record_status": "Operational; no public site-specific connection case found",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 2,
        "unpopulated_detailed_fields": 14,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "transmission_interconnection_provider",
          "site_planned_mw"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-d1b62579c6be3fe8",
      "epoch_name": "Core42 Lake Mariner",
      "country": "United States",
      "state_province": "NY",
      "address": "7725 Lake Rd, Barker, NY 14012",
      "current_it_power_mw": 58,
      "current_h100_equivalents": 71753.4108135422,
      "grid_or_queue_jurisdiction": "NYISO",
      "scope": "within_registry_geography",
      "status": "site_specific_queue_verified",
      "site_specific_queue_id": "1670",
      "site_specific_queue_name": "Lake Mariner Data II",
      "site_specific_capacity_mw": 250,
      "primary_source_url": "https://www.nyiso.com/documents/20142/1407078/NYISO-Interconnection-Queue.xlsx",
      "source_type": "NYISO Load Projects queue",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "Same Lake Mariner campus as the Epoch Core42 record; queue is a request/phase and is not a 1:1 duplicate of Epoch IT power.",
      "confidence": "high",
      "next_action": "Maintain primary-source citation and reconcile queue/service MW against Epoch IT MW.",
      "lat": 42.9,
      "lon": -75.5,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_queue",
          "authority": "NYISO",
          "record_id": "1670",
          "record_name": "Lake Mariner Data II",
          "capacity_mw": 250,
          "source_url": "https://www.nyiso.com/documents/20142/1407078/NYISO-Interconnection-Queue.xlsx",
          "source_kind": "official queue workbook",
          "confidence": "high",
          "basis": "Same Lake Mariner campus as the Epoch Core42 record; the queue request is not treated as a duplicate of Epoch IT power."
        }
      ],
      "existing_queue_crosswalk": {
        "id": "1670",
        "name": "Lake Mariner Data II",
        "capacity_mw": 250
      },
      "connection_match_status": "SITE_SPECIFIC_QUEUE_VERIFIED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Core42 #confident / G42 #likely",
      "utility_or_service_provider": "NYISO",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": 250,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "site_specific_queue_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 4,
        "unpopulated_detailed_fields": 12,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-71d0091a05448224",
      "epoch_name": "Microsoft SAT40",
      "country": "United States",
      "state_province": "TX",
      "address": "15000 Lambda Drive, San Antonio, TX 78245",
      "current_it_power_mw": 75,
      "current_h100_equivalents": 64679.13087417888,
      "grid_or_queue_jurisdiction": "ERCOT",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.ercot.com/services/rq/large-load-integration",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TX is assigned to the ERCOT queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 31.1,
      "lon": -99.4,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Karnes Electric Cooperative",
          "record_name": "SAT40 utility/grid-operator record",
          "source_url": "https://www.datacenter.fyi/state/tx",
          "source_kind": "secondary public-record index",
          "confidence": "medium",
          "basis": "The current Texas public-record index lists SAT40 under Microsoft and identifies Karnes Electric Cooperative as the grid operator. This supports a site/project utility relationship but not a unique ERCOT queue ID."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Microsoft",
      "utility_or_service_provider": "Karnes Electric Cooperative",
      "utility_type": "electric cooperative",
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 75,
      "public_record_status": "TDLR project Review Complete; site-level connection record not publicly identified in reviewed sources",
      "request_or_study_date": "2023-06-15",
      "service_or_approval_date": "2023-09-15",
      "target_in_service_date": null,
      "connection_research_notes": "2026-09-27",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 6,
        "unpopulated_detailed_fields": 10,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-c89a3269719f868a",
      "epoch_name": "STACK Infrastructure NVA02",
      "country": "United States",
      "state_province": "VA",
      "address": "9590 Hornbaker Rd, Manassas, VA 20109",
      "current_it_power_mw": 85,
      "current_h100_equivalents": 61141.99090449722,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State VA is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 37.5,
      "lon": -78.7,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_service",
          "authority": "NOVEC",
          "record_name": "NVA02 dedicated substations",
          "capacity_mw": 600,
          "source_url": "https://www.stackinfra.com/locations/americas/northern-virginia/nva02/",
          "source_kind": "official STACK facility disclosure",
          "confidence": "high",
          "basis": "STACK states NVA02 has two dedicated 300 MW onsite substations from Northern Virginia Electric Cooperative."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "STACK Infrastructure NVA02",
      "utility_or_service_provider": "NOVEC",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-29fb769630142638",
      "epoch_name": "Anthropic Lake Mariner",
      "country": "United States",
      "state_province": "NY",
      "address": "7725 Lake Rd, Barker, NY 14012",
      "current_it_power_mw": 42,
      "current_h100_equivalents": 58564.93178372915,
      "grid_or_queue_jurisdiction": "NYISO",
      "scope": "within_registry_geography",
      "status": "site_specific_queue_verified",
      "site_specific_queue_id": "1670",
      "site_specific_queue_name": "Lake Mariner Data II",
      "site_specific_capacity_mw": 250,
      "primary_source_url": "https://www.nyiso.com/documents/20142/1407078/NYISO-Interconnection-Queue.xlsx",
      "source_type": "NYISO Load Projects queue",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "NYISO Q1670 Lake Mariner Data II in Niagara County; campus identity aligns with Epoch's Barker site.",
      "confidence": "high",
      "next_action": "Maintain primary-source citation and reconcile queue/service MW against Epoch IT MW.",
      "lat": 42.9,
      "lon": -75.5,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_queue",
          "authority": "NYISO",
          "record_id": "1670",
          "record_name": "Lake Mariner Data II",
          "capacity_mw": 250,
          "source_url": "https://www.nyiso.com/documents/20142/1407078/NYISO-Interconnection-Queue.xlsx",
          "source_kind": "official queue workbook",
          "confidence": "high",
          "basis": "Epoch site address is 7725 Lake Rd, Barker, NY; NYISO Q1670 is Lake Mariner Data II in Niagara County."
        }
      ],
      "existing_queue_crosswalk": {
        "id": "1670",
        "name": "Lake Mariner Data II",
        "capacity_mw": 250
      },
      "connection_match_status": "SITE_SPECIFIC_QUEUE_VERIFIED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "AI XPV Platform #confident / Anthropic #likely",
      "utility_or_service_provider": "NYISO",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": 250,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "site_specific_queue_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 4,
        "unpopulated_detailed_fields": 12,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-781cbfae186209ad",
      "epoch_name": "Microsoft-Nebius New Jersey",
      "country": "United States",
      "state_province": "NJ",
      "address": "3963 S Lincoln Ave, Vineland, New Jersey",
      "current_it_power_mw": 50,
      "current_h100_equivalents": 56846.89236988378,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State NJ is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 40.2,
      "lon": -74.7,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_SPECIFIC_BEHIND_THE_METER_SERVICE_EVIDENCE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Nebius / DataOne; Microsoft offtaker",
      "utility_or_service_provider": "Bloom Energy",
      "utility_type": "behind-the-meter generation / power services",
      "transmission_interconnection_provider": "PJM",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": 250,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 300,
      "public_record_status": "Power supplied in part by on-site Bloom Energy fuel cells; PJM grid relationship remains separate; no public PJM queue ID located",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": "2026",
      "connection_research_notes": "The power figures are on-site generation figures, not a PJM interconnection capacity. Microsoft/Nebius commercial relationship is also distinct from electricity service.",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 7,
        "unpopulated_detailed_fields": 9,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "transmission_interconnection_provider",
          "service_capacity_mw",
          "site_planned_mw",
          "target_in_service_date",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-f48a533b01898dfd",
      "epoch_name": "CoreWeave Norway",
      "country": "Norway",
      "state_province": "",
      "address": "Stølevegen 39, 4715 Øvrebø, Norway",
      "current_it_power_mw": 42,
      "current_h100_equivalents": 50773.11773623042,
      "grid_or_queue_jurisdiction": "Statnett + local distribution network connections",
      "scope": "outside_registry_geography",
      "status": "country_connection_system_mapped",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": null,
      "source_type": "national / local connection system",
      "source_date": "2026-09-26",
      "next_research_sources": "Statnett connection process",
      "match_basis": "Epoch site is outside the current U.S./Canada nine-market registry geography; a national/utility connection system is recorded as the relevant external jurisdiction.",
      "confidence": "jurisdiction",
      "next_action": "Search the named national/transmission/distribution connection system plus regulator and utility records for a site-specific connection record.",
      "lat": 60.472,
      "lon": 8.4689,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "CoreWeave; possible OpenAI user",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": "Statnett / local distribution network",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 42,
      "public_record_status": "Operational; no public site-specific connection case found",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 2,
        "unpopulated_detailed_fields": 14,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "transmission_interconnection_provider",
          "site_planned_mw"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-41dea3fb46d2e6a8",
      "epoch_name": "Nebius Mantsala",
      "country": "Finland",
      "state_province": "",
      "address": null,
      "current_it_power_mw": 75,
      "current_h100_equivalents": 48527.92066700354,
      "grid_or_queue_jurisdiction": "Fingrid + local distribution network connections",
      "scope": "outside_registry_geography",
      "status": "country_connection_system_mapped",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": null,
      "source_type": "national / local connection system",
      "source_date": "2026-09-26",
      "next_research_sources": "Fingrid main-grid connection/open data",
      "match_basis": "Epoch site is outside the current U.S./Canada nine-market registry geography; a national/utility connection system is recorded as the relevant external jurisdiction.",
      "confidence": "jurisdiction",
      "next_action": "Search the named national/transmission/distribution connection system plus regulator and utility records for a site-specific connection record.",
      "lat": 61.9241,
      "lon": 25.7482,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Nebius",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": "Fingrid / local distribution network",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 75,
      "public_record_status": "Operational; no public site-specific connection case found",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 2,
        "unpopulated_detailed_fields": 14,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "transmission_interconnection_provider",
          "site_planned_mw"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-827d7832237170bd",
      "epoch_name": "Southgate Melbourne",
      "country": "Australia",
      "state_province": "",
      "address": null,
      "current_it_power_mw": 41,
      "current_h100_equivalents": 46488.12531581607,
      "grid_or_queue_jurisdiction": "AEMO + local network service provider connections",
      "scope": "outside_registry_geography",
      "status": "country_connection_system_mapped",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": null,
      "source_type": "national market / NSP connection system",
      "source_date": "2026-09-26",
      "next_research_sources": "AEMO NEM Registration; AEMO connection process / scorecard",
      "match_basis": "Epoch site is outside the current U.S./Canada nine-market registry geography; a national/utility connection system is recorded as the relevant external jurisdiction.",
      "confidence": "jurisdiction",
      "next_action": "Search the named national/transmission/distribution connection system plus regulator and utility records for a site-specific connection record.",
      "lat": -25.2744,
      "lon": 133.7751,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Firmus",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": "AEMO / local network service provider",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 41,
      "public_record_status": "Operational; no public site-specific connection case found",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 2,
        "unpopulated_detailed_fields": 14,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "transmission_interconnection_provider",
          "site_planned_mw"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-ee5c7acdbc729ef8",
      "epoch_name": "Stream Phoenix",
      "country": "United States",
      "state_province": "AZ",
      "address": "2950 S. Litchfield Road",
      "current_it_power_mw": 64,
      "current_h100_equivalents": 46134.4113188479,
      "grid_or_queue_jurisdiction": "WECC / Arizona serving utilities (APS / SRP)",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/az/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State AZ is assigned to the WECC / Arizona serving utilities (APS / SRP) queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 39.8,
      "lon": -98.6,
      "precision": "country centroid",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_SPECIFIC_UTILITY_SERVICE_EVIDENCE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Stream Data Centers",
      "utility_or_service_provider": "Arizona Public Service (APS)",
      "utility_type": "electric utility",
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 280,
      "public_record_status": "Planned/operating campus with public APS utility linkage; no site-specific utility case or queue ID located",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": "APS is retained as the utility; planned facility capacity is not treated as utility service capacity.",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 4,
        "unpopulated_detailed_fields": 12,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "site_planned_mw",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-0355f445ca6cbed4",
      "epoch_name": "Microsoft SAT14",
      "country": "United States",
      "state_province": "TX",
      "address": "3545 Wiseman Boulevard, San Antonio, TX 78251",
      "current_it_power_mw": 47,
      "current_h100_equivalents": 45174.33046993431,
      "grid_or_queue_jurisdiction": "ERCOT",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.ercot.com/services/rq/large-load-integration",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TX is assigned to the ERCOT queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 31.1,
      "lon": -99.4,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Karnes Electric Cooperative",
          "record_name": "SAT14 utility/grid-operator record",
          "source_url": "https://www.datacenter.fyi/state/tx",
          "source_kind": "secondary public-record index",
          "confidence": "medium",
          "basis": "The current Texas public-record index lists SAT14 phases under Microsoft and identifies Karnes Electric Cooperative as the grid operator. This supports a site/project utility relationship but not a unique ERCOT queue ID."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Microsoft",
      "utility_or_service_provider": "Karnes Electric Cooperative",
      "utility_type": "electric cooperative",
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 47,
      "public_record_status": "Multiple TDLR phases documented; no public ERCOT queue/service identifier located",
      "request_or_study_date": "2021-10-01",
      "service_or_approval_date": "2026-03-31",
      "target_in_service_date": null,
      "connection_research_notes": "2026-09-27",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 6,
        "unpopulated_detailed_fields": 10,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-96d37578ca36f86c",
      "epoch_name": "Vantage TX1",
      "country": "United States",
      "state_province": "TX",
      "address": "14720 Omicron Dr, San Antonio, TX 78245",
      "current_it_power_mw": 32,
      "current_h100_equivalents": 38706.417382516425,
      "grid_or_queue_jurisdiction": "ERCOT",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.ercot.com/services/rq/large-load-integration",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TX is assigned to the ERCOT queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 31.1,
      "lon": -99.4,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_project_record",
          "authority": "Texas Department of Licensing and Regulation",
          "record_id": "TX11",
          "record_name": "Vantage TX11 / TX1 project",
          "source_url": "https://www.tdlr.texas.gov/",
          "source_kind": "state construction/project record",
          "confidence": "high",
          "basis": "State construction records identify project TX11 at 14720 Omicron Drive under Vantage Data Centers TX1 LLC; this establishes the physical project identity but not a queue ID."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Vantage TX1",
      "utility_or_service_provider": "Texas Department of Licensing and Regulation",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-8696ef81d91560a9",
      "epoch_name": "CoreWeave Dalton 1 & 2",
      "country": "United States",
      "state_province": "GA",
      "address": "2205 Industrial South Rd, Dalton, GA, 30721",
      "current_it_power_mw": 28,
      "current_h100_equivalents": 32238.504295098533,
      "grid_or_queue_jurisdiction": "SERC / Georgia transmission providers",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/ga/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State GA is assigned to the SERC / Georgia transmission providers queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 32.7,
      "lon": -83.4,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_service_contract",
          "authority": "Dalton Utilities",
          "record_name": "DU electric service agreement / Dalton Campuses",
          "capacity_mw": 270,
          "source_url": "https://www.sec.gov/Archives/edgar/data/1839341/000119312526165121/d149019dex992.htm",
          "source_kind": "SEC-filed electric service agreement",
          "confidence": "high",
          "basis": "SEC filing states Dalton campuses are supplied by Dalton Utilities and Dalton 1 + Dalton 4 have access to 270 MW in aggregate, with additional capacity arrangements."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "CoreWeave #confident / OpenAI #speculative",
      "utility_or_service_provider": "Dalton Utilities",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-e20c2909085b37fd",
      "epoch_name": "Alibaba Zhangbei",
      "country": "China",
      "state_province": "",
      "address": "Alibaba Zhangbei Yun Calculation Data Center, Zhangbei County, Zhangjiakou, Hebei, China, 076471",
      "current_it_power_mw": 169,
      "current_h100_equivalents": 31884.79029813037,
      "grid_or_queue_jurisdiction": "China State Grid / provincial grid connection process",
      "scope": "outside_registry_geography",
      "status": "country_connection_system_mapped",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": null,
      "source_type": "national / provincial connection system",
      "source_date": "2026-09-26",
      "next_research_sources": "State Grid / provincial grid",
      "match_basis": "Epoch site is outside the current U.S./Canada nine-market registry geography; a national/utility connection system is recorded as the relevant external jurisdiction.",
      "confidence": "jurisdiction",
      "next_action": "Search the named national/transmission/distribution connection system plus regulator and utility records for a site-specific connection record.",
      "lat": 35.8617,
      "lon": 104.1954,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Alibaba",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": "China State Grid / Hebei provincial grid system",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 169,
      "public_record_status": "Operational; no public site-specific connection case found",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 2,
        "unpopulated_detailed_fields": 14,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "transmission_interconnection_provider",
          "site_planned_mw"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-8baa344f9717520c",
      "epoch_name": "Start Campus Sines Data Campus",
      "country": "Portugal",
      "state_province": "",
      "address": "Start Campus - Sustainable Data Center Services, Sines, Portugal",
      "current_it_power_mw": 33,
      "current_h100_equivalents": 31834.259727134915,
      "grid_or_queue_jurisdiction": "REN + local network connection process",
      "scope": "outside_registry_geography",
      "status": "country_connection_system_mapped",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": null,
      "source_type": "transmission / distribution connection system",
      "source_date": "2026-09-26",
      "next_research_sources": "REN; E-REDES",
      "match_basis": "Epoch site is outside the current U.S./Canada nine-market registry geography; a national/utility connection system is recorded as the relevant external jurisdiction.",
      "confidence": "jurisdiction",
      "next_action": "Search the named national/transmission/distribution connection system plus regulator and utility records for a site-specific connection record.",
      "lat": 39.3999,
      "lon": -8.2245,
      "precision": "country centroid",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_SPECIFIC_GRID_CAPACITY_EVIDENCE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Start Campus",
      "utility_or_service_provider": "REN (Redes Energéticas Nacionais)",
      "utility_type": "transmission system operator / grid capacity allocation",
      "transmission_interconnection_provider": "REN",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": 1200,
      "approved_capacity_mw": 1200,
      "contract_ceiling_mw": null,
      "site_planned_mw": 1200,
      "public_record_status": "Grid power fully secured for 1.2 GW campus; SIN01 operational and later buildings phased",
      "request_or_study_date": "2024-08-08",
      "service_or_approval_date": "2024-08-08",
      "target_in_service_date": "2030",
      "connection_research_notes": "1.2 GW is secured campus IT capacity/grid access, not current measured load and not a queue ID.",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 10,
        "unpopulated_detailed_fields": 6,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "transmission_interconnection_provider",
          "service_capacity_mw",
          "approved_capacity_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "contract_ceiling_mw"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-495a9afde5e4b96c",
      "epoch_name": "xAI QTS Atlanta",
      "country": "United States",
      "state_province": "GA",
      "address": "1025 Jefferson Street NW, Atlanta, GA 30318",
      "current_it_power_mw": 17.32971,
      "current_h100_equivalents": 11470.43961596766,
      "grid_or_queue_jurisdiction": "SERC / Georgia transmission providers",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/ga/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State GA is assigned to the SERC / Georgia transmission providers queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 32.7,
      "lon": -83.4,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_SPECIFIC_UTILITY_SERVICE_EVIDENCE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "xAI / SpaceXAI; QTS campus",
      "utility_or_service_provider": "Georgia Power",
      "utility_type": "electric utility",
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 17,
      "public_record_status": "Operational xAI cluster at QTS Atlanta; public facility records identify Georgia Power as utility",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": "xAI occupies part of a multi-tenant QTS building; utility capacity should not be attributed wholesale to xAI.",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 4,
        "unpopulated_detailed_fields": 12,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "site_planned_mw",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-f1a70be0079d215a",
      "epoch_name": "Nscale Keflavik",
      "country": "Iceland",
      "state_province": "",
      "address": "Valhallarbraut 868, 262 Reykjanesbær, Iceland",
      "current_it_power_mw": 5.11,
      "current_h100_equivalents": 5821.121778676099,
      "grid_or_queue_jurisdiction": "Landsnet + local distribution network connections",
      "scope": "outside_registry_geography",
      "status": "country_connection_system_mapped",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": null,
      "source_type": "transmission / distribution connection system",
      "source_date": "2026-09-26",
      "next_research_sources": "Landsnet",
      "match_basis": "Epoch site is outside the current U.S./Canada nine-market registry geography; a national/utility connection system is recorded as the relevant external jurisdiction.",
      "confidence": "jurisdiction",
      "next_action": "Search the named national/transmission/distribution connection system plus regulator and utility records for a site-specific connection record.",
      "lat": 64.9631,
      "lon": -19.0208,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Nscale",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": "Landsnet / local distribution network",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 5.11,
      "public_record_status": "Site identity documented; no public site-specific connection case found",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 2,
        "unpopulated_detailed_fields": 14,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "transmission_interconnection_provider",
          "site_planned_mw"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-5b05fa7b682be282",
      "epoch_name": "Anthropic Barber Lake",
      "country": "United States",
      "state_province": "TX",
      "address": null,
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "ERCOT",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.ercot.com/services/rq/large-load-integration",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TX is assigned to the ERCOT queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 39.8,
      "lon": -98.6,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Anthropic / Cipher Mining",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 207,
      "public_record_status": "Under construction; public site identity and projected IT power documented; no site-specific queue/service record located",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": "2026-12",
      "connection_research_notes": "The closest same-area raw queue candidate, 28INR0119 / 1190 Barber Lake Switch 138kV / 341.8 MW, is a Rabbit Hollow Energy Storage BESS and is rejected as unrelated generation/storage.",
      "alternative_candidates": [
        {
          "candidate_id": "28INR0119",
          "candidate_record": "Rabbit Hollow Energy Storage",
          "candidate_poi": "1190 Barber Lake Switch 138kV",
          "candidate_capacity_mw": 341.8,
          "candidate_status": "Facilities Study",
          "rejected_reason": "Confirmed battery-energy-storage queue row; no Anthropic/Cipher identity and not a data-center service request."
        }
      ],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 3,
        "unpopulated_detailed_fields": 13,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "site_planned_mw",
          "target_in_service_date",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-7648e1438308fdae",
      "epoch_name": "CoreWeave Lancaster Greenfield site",
      "country": "United States",
      "state_province": "PA",
      "address": "216 Greenfield Rd, Lancaster, PA \n",
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State PA is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 40.9,
      "lon": -77.8,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_facility_utility_evidence",
          "authority": "PPL Electric",
          "record_name": "CoreWeave Lancaster data center",
          "source_url": "https://registry.deploy.report/datacenters/facilities/coreweave-lancaster-pa",
          "source_kind": "secondary verified facility registry",
          "confidence": "medium",
          "basis": "DEPLOY identifies the exact 216 Greenfield Road CoreWeave Lancaster facility; the broader research record identifies PPL Electric as the serving utility."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "CoreWeave #confident / OpenAI #speculative",
      "utility_or_service_provider": "PPL Electric",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-65e758d676dc06d6",
      "epoch_name": "CoreWeave Muskogee OK",
      "country": "United States",
      "state_province": "OK",
      "address": "1525 W 43rd St S, Muskogee, OK 74401, USA",
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "SPP",
      "scope": "within_registry_geography",
      "status": "public_service_contract_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": "OG&E electric service agreement",
      "site_specific_capacity_mw": 100,
      "primary_source_url": "https://investors.corescientific.com/sec-filings/all-sec-filings/content/0001193125-26-165121/d149019dex992.htm",
      "source_type": "SEC-filed electric service agreement",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "Public filing states power is supplied under an OG&E electric service agreement with estimated maximum demand of 100,000 kW for the Muskogee campus.",
      "confidence": "high",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 35.6,
      "lon": -97.5,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_service_contract",
          "authority": "OG&E",
          "record_name": "OG&E electric service agreement",
          "capacity_mw": 100,
          "source_url": "https://www.sec.gov/Archives/edgar/data/1839341/000119312526165121/d149019dex992.htm",
          "source_kind": "SEC-filed electric service agreement",
          "confidence": "high",
          "basis": "SEC filing states power for the Muskogee campus is supplied by OG&E and gives estimated maximum demand of 100,000 kW."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "PUBLIC_SERVICE_CONTRACT_VERIFIED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "CoreWeave #confident / OpenAI #speculative",
      "utility_or_service_provider": "OG&E",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": 100,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "public_service_contract_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 3,
        "unpopulated_detailed_fields": 13,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-4569f5444951b2fd",
      "epoch_name": "Crusoe Abilene Expansion",
      "country": "United States",
      "state_province": "TX",
      "address": "5502 Spinks Rd, Abilene, TX 79601",
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "ERCOT",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.ercot.com/services/rq/large-load-integration",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TX is assigned to the ERCOT queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 31.1,
      "lon": -99.4,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_SPECIFIC_GRID_IDENTITY_NO_QUEUE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Crusoe; Microsoft customer relationship",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": "ERCOT system",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 900,
      "public_record_status": "Under construction; ERCOT grid connection identified; no public site-specific queue ID/service case located",
      "request_or_study_date": "2026-03-27",
      "service_or_approval_date": null,
      "target_in_service_date": "2027",
      "connection_research_notes": "The campus is adjacent to the existing Abilene site. ERCOT is the grid operator; no unique public queue ID was located.",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 5,
        "unpopulated_detailed_fields": 11,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "transmission_interconnection_provider",
          "site_planned_mw",
          "request_or_study_date",
          "target_in_service_date",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "service_or_approval_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-dadec9d6ef7fca88",
      "epoch_name": "EcoDataCenter 2",
      "country": "Sweden",
      "state_province": "",
      "address": "Kvarnsvedsvägen 420, 784 66 Borlänge, Sweden",
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "Svenska kraftnät + local distribution network connections",
      "scope": "outside_registry_geography",
      "status": "country_connection_system_mapped",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": null,
      "source_type": "national / local connection system",
      "source_date": "2026-09-26",
      "next_research_sources": "Svenska kraftnät connection queue",
      "match_basis": "Epoch site is outside the current U.S./Canada nine-market registry geography; a national/utility connection system is recorded as the relevant external jurisdiction.",
      "confidence": "jurisdiction",
      "next_action": "Search the named national/transmission/distribution connection system plus regulator and utility records for a site-specific connection record.",
      "lat": 60.1282,
      "lon": 18.6435,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "EcoDataCenter / Mistral AI",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": "Svenska kraftnät / local distribution network",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 48,
      "public_record_status": "Under construction; no public site-specific connection case found",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 2,
        "unpopulated_detailed_fields": 14,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "transmission_interconnection_provider",
          "site_planned_mw"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-bbf05f2d8903eccc",
      "epoch_name": "Goodnight",
      "country": "United States",
      "state_province": "TX",
      "address": "10001 Lima Rd, Claude, TX 79019",
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "ERCOT",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.ercot.com/services/rq/large-load-integration",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TX is assigned to the ERCOT queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 31.1,
      "lon": -99.4,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_regulatory_support",
          "authority": "Texas Commission on Environmental Quality",
          "record_id": "Permit 182880 / PSDTX1698 / GHGPSDTX268",
          "record_name": "Goodnight Data Center permit",
          "source_url": "https://www.tceq.texas.gov/",
          "source_kind": "state environmental permit record",
          "confidence": "high",
          "basis": "TCEQ permitting records identify the Goodnight Data Center and Crusoe Energy Systems as applicant; this is supporting site evidence, not a queue ID."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google #speculative / Google DeepMind #speculative",
      "utility_or_service_provider": "Texas Commission on Environmental Quality",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-2d6a8403fde79650",
      "epoch_name": "Google Cedar Rapids",
      "country": "United States",
      "state_province": "IA",
      "address": "5800 EDGEWOOD RD SW CEDAR RAPIDS, IA 52404",
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "MISO",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.misoenergy.org/api/giqueue/getprojects",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State IA is assigned to the MISO queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 42.1,
      "lon": -93.5,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Alliant Energy",
          "record_name": "Google Big Cedar data-center project",
          "source_url": "https://www.alliantenergy.com/news/news-center/2025/06/060425-googlebigcedarannouncement",
          "source_kind": "official utility disclosure",
          "confidence": "high",
          "basis": "Alliant officially confirmed Google's Cedar Rapids data-center project at Alliant's Big Cedar Industrial Center."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google #confident / Google DeepMind #speculative",
      "utility_or_service_provider": "Alliant Energy",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-f340a33a5ef18d4f",
      "epoch_name": "Google Fort Wayne",
      "country": "United States",
      "state_province": "IN",
      "address": "6015 Adams Center Road, Fort Wayne, IN 46806",
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "MISO",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.misoenergy.org/api/giqueue/getprojects",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State IN is assigned to the MISO queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 39.9,
      "lon": -86.3,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_regulatory",
          "authority": "Indiana Michigan Power / Indiana Utility Regulatory Commission",
          "record_id": "Cause No. 46276",
          "record_name": "Google Fort Wayne energization",
          "source_url": "https://datacenterdata.io/insights/updates/u/b721b76c4739/",
          "source_kind": "secondary record reproducing an official IURC order",
          "confidence": "high",
          "basis": "The April 29, 2026 IURC final order records that I&M energized Google's Fort Wayne site in November 2024; the underlying official order is Cause No. 46276."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Google #confident / Google DeepMind #speculative",
      "utility_or_service_provider": "Indiana Michigan Power / Indiana Utility Regulatory Commission",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-177c53f92d72ec4a",
      "epoch_name": "Meta Bowling Green",
      "country": "United States",
      "state_province": "OH",
      "address": "12356 Middleton Pike, Bowling Green, OH 43402",
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State OH is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 40.4,
      "lon": -82.8,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Toledo Edison",
          "record_name": "Meta Bowling Green energy planning",
          "source_url": "https://datacenters.atmeta.com/2025/04/hello-bowling-green/",
          "source_kind": "official Meta disclosure",
          "confidence": "high",
          "basis": "Meta states it worked closely with Toledo Edison from the beginning to plan the site's energy needs."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta / Meta",
      "utility_or_service_provider": "Toledo Edison",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-bbcf0efa8bcebd41",
      "epoch_name": "Meta Hyperion",
      "country": "United States",
      "state_province": "LA",
      "address": "Holly Ridge, LA 71269",
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "MISO",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.misoenergy.org/api/giqueue/getprojects",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State LA is assigned to the MISO queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 31,
      "lon": -92,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_regulatory",
          "authority": "Louisiana Public Service Commission / Entergy Louisiana",
          "record_name": "Large-load service proceedings for Meta Hyperion",
          "source_url": "https://www.lpsc.louisiana.gov/",
          "source_kind": "state commission docket family",
          "confidence": "medium",
          "basis": "Louisiana public-service records identify large-load service proceedings associated with the Holly Ridge/Hyperion campus and Entergy Louisiana."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta #confident / Meta #confident",
      "utility_or_service_provider": "Louisiana Public Service Commission / Entergy Louisiana",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-1b7cb9c2b0eb479f",
      "epoch_name": "Microsoft Narvik Norway",
      "country": "Norway",
      "state_province": "",
      "address": null,
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "Statnett + local distribution network connections",
      "scope": "outside_registry_geography",
      "status": "country_connection_system_mapped",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": null,
      "source_type": "national / local connection system",
      "source_date": "2026-09-26",
      "next_research_sources": "Statnett connection process",
      "match_basis": "Epoch site is outside the current U.S./Canada nine-market registry geography; a national/utility connection system is recorded as the relevant external jurisdiction.",
      "confidence": "jurisdiction",
      "next_action": "Search the named national/transmission/distribution connection system plus regulator and utility records for a site-specific connection record.",
      "lat": 60.472,
      "lon": 8.4689,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Microsoft / Nscale",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": "Statnett / local distribution network",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 92,
      "public_record_status": "Under construction; local hydropower context public; no site-specific connection case found",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": "No public utility/queue identifier was found in the reviewed record set.",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 3,
        "unpopulated_detailed_fields": 13,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "transmission_interconnection_provider",
          "site_planned_mw",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-dc6199921ba82b85",
      "epoch_name": "OpenAI Stargate Lordstown",
      "country": "United States",
      "state_province": "OH",
      "address": "2300 Hallock Young Rd, Warren, OH 44481",
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "PJM",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.pjm.com/planning/service-requests",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State OH is assigned to the PJM queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 40.4,
      "lon": -82.8,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "OpenAI; SoftBank / Foxconn project",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": "PJM system",
      "substation": "Foxconn plant substation (site context; exact substation name not published)",
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 300,
      "public_record_status": "Early-stage site; likely grid-served through existing Foxconn substation context; no public data-center queue/service record identified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": "The existing Foxconn substation is site context, not a queue or service record. No site-specific PJM identifier was located.",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 4,
        "unpopulated_detailed_fields": 12,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "transmission_interconnection_provider",
          "substation",
          "site_planned_mw",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-145ed5861bdf2982",
      "epoch_name": "OpenAI Stargate Michigan",
      "country": "United States",
      "state_province": "MI",
      "address": null,
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "MISO",
      "scope": "within_registry_geography",
      "status": "public_service_contract_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": "DTE special-contract / Stargate Michigan",
      "site_specific_capacity_mw": 1383,
      "primary_source_url": "https://www.michigan.gov/som/data-centers",
      "source_type": "Michigan Public Service Commission special-contract approval",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "Michigan's official data-center page identifies MPSC approval of DTE Electric energy contracts; Epoch's site record cites the approval reporting 1,383 MW site capacity.",
      "confidence": "high",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 39.8,
      "lon": -98.6,
      "precision": "country centroid",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_regulatory",
          "authority": "Michigan Public Service Commission / DTE Electric",
          "record_name": "DTE special-contract approval / Stargate Michigan",
          "capacity_mw": 1383,
          "source_url": "https://www.michigan.gov/som/data-centers",
          "source_kind": "state government / commission record",
          "confidence": "high",
          "basis": "Michigan's official data-center material identifies MPSC approval of DTE Electric energy contracts; the cited approval reports 1,383 MW site capacity."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "PUBLIC_SERVICE_CONTRACT_VERIFIED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Oracle #confident / OpenAI #confident",
      "utility_or_service_provider": "Michigan Public Service Commission / DTE Electric",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": 1383,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "public_service_contract_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 3,
        "unpopulated_detailed_fields": 13,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-e3aa5f34aa5c4a7b",
      "epoch_name": "OpenAI Stargate Milam",
      "country": "United States",
      "state_province": "TX",
      "address": null,
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "ERCOT",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.ercot.com/services/rq/large-load-integration",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TX is assigned to the ERCOT queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 39.8,
      "lon": -98.6,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_specific_power_infrastructure_partner",
          "authority": "SB Energy / OpenAI",
          "record_name": "Stargate Milam County powered infrastructure partnership",
          "source_url": "https://openai.com/index/stargate-sb-energy-partnership/",
          "source_kind": "operator official disclosure",
          "confidence": "high",
          "basis": "OpenAI states it selected SB Energy to build and operate the 1.2 GW Milam County data-center site and describes SB Energy as the development/execution partner for the associated energy infrastructure. This identifies the energy-infrastructure counterparty, not a separate grid utility or queue ID."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "OpenAI / SoftBank SB Energy",
      "utility_or_service_provider": "SB Energy (powered-infrastructure partner; grid utility not separately established)",
      "utility_type": "energy infrastructure provider",
      "transmission_interconnection_provider": "ERCOT system",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 1200,
      "public_record_status": "Announced / developing Milam County site; public site-level connection identifier not located",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": "2026-09-27",
      "alternative_candidates": [
        {
          "candidate_id": "26INR0633",
          "candidate_record": "Betel Storage II",
          "candidate_poi": "3377 Little Pond 345",
          "candidate_capacity_mw": 500,
          "rejected_reason": "Explicit BESS/storage project; developer/customer identity does not match Stargate/SB Energy."
        },
        {
          "candidate_id": "26INR0630",
          "candidate_record": "Betel Storage I",
          "candidate_poi": "3377 Little Pond Switch 345",
          "candidate_capacity_mw": 500,
          "rejected_reason": "Explicit BESS/storage project; unrelated to data-center load."
        }
      ],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 5,
        "unpopulated_detailed_fields": 11,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "transmission_interconnection_provider",
          "site_planned_mw",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-3816121e8d72fe04",
      "epoch_name": "OpenAI Stargate New Mexico",
      "country": "United States",
      "state_province": "NM",
      "address": null,
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "WECC / PNM and other New Mexico serving utilities",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/nm/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State NM is assigned to the WECC / PNM and other New Mexico serving utilities queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 39.8,
      "lon": -98.6,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_level_regional_utility_context",
          "authority": "El Paso Electric",
          "record_name": "Santa Teresa / Doña Ana County utility context",
          "source_url": "https://registry.deploy.report/datacenters/stargate-dona-ana-county-new-mexico",
          "source_kind": "secondary sourced facility registry",
          "confidence": "medium",
          "basis": "The retained facility record identifies El Paso Electric as the regional utility serving the Santa Teresa / Doña Ana County area. It does not establish a site-specific service contract or queue identifier."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "OpenAI",
      "utility_or_service_provider": "El Paso Electric (regional utility; site-specific service not separately established)",
      "utility_type": "regional electric utility",
      "transmission_interconnection_provider": "WECC / PNM serving system",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 2200,
      "public_record_status": "Announced/developing Doña Ana County site; no public site-specific queue/service case located",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": "2026-09-27",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 5,
        "unpopulated_detailed_fields": 11,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "transmission_interconnection_provider",
          "site_planned_mw",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-b427a75f62d61aae",
      "epoch_name": "OpenAI Stargate Shackelford",
      "country": "United States",
      "state_province": "TX",
      "address": "175 Private Road 1604, Abilene, TX 79601, Shackelford County",
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "ERCOT",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.ercot.com/services/rq/large-load-integration",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State TX is assigned to the ERCOT queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 31.1,
      "lon": -99.4,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "OpenAI / Vantage",
      "utility_or_service_provider": null,
      "utility_type": null,
      "transmission_interconnection_provider": "ERCOT system",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 1400,
      "public_record_status": "Under construction; no public data-center queue/service record located",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": "Raw ERCOT candidate 26INR0500 is a 206.5 MW BESS at 1442 CFRSW 345kV and is rejected as unrelated storage, despite county-name similarity.",
      "alternative_candidates": [
        {
          "candidate_id": "26INR0500",
          "candidate_record": "Shackleford BESS",
          "candidate_poi": "1442 CFRSW 345kV",
          "candidate_capacity_mw": 206.5,
          "rejected_reason": "Explicit BESS/storage queue row with unrelated developer; not a data-center request."
        }
      ],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 3,
        "unpopulated_detailed_fields": 13,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "transmission_interconnection_provider",
          "site_planned_mw",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-661288625d17662a",
      "epoch_name": "OpenAI Stargate UAE",
      "country": "United Arab Emirates",
      "state_province": "",
      "address": "Nexus L&T Project Office, Al Bihouth, Al Dhafrah, Abu Dhabi, United Arab Emirates",
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "UAE transmission / local distribution connection process",
      "scope": "outside_registry_geography",
      "status": "country_connection_system_mapped",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": null,
      "source_type": "utility connection system",
      "source_date": "2026-09-26",
      "next_research_sources": "EWEC / local network operators",
      "match_basis": "Epoch site is outside the current U.S./Canada nine-market registry geography; a national/utility connection system is recorded as the relevant external jurisdiction.",
      "confidence": "jurisdiction",
      "next_action": "Search the named national/transmission/distribution connection system plus regulator and utility records for a site-specific connection record.",
      "lat": 23.4241,
      "lon": 53.8478,
      "precision": "country centroid",
      "site_level_evidence_status": "no_match_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "type": "site_level_grid_operator_context",
          "authority": "Emirates Water and Electricity Company (EWEC)",
          "record_name": "Stargate UAE grid-operator context",
          "source_url": "https://registry.deploy.report/datacenters/stargate-uae-abu-dhabi",
          "source_kind": "secondary sourced facility registry",
          "confidence": "medium",
          "basis": "The retained facility record identifies EWEC as the grid operator for the Abu Dhabi Stargate UAE cluster. Exact interconnection/service details are not published in the retained record."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "NO_MATCH_FOUND_SITE_SPECIFIC_QUEUE_OR_SERVICE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "OpenAI / Stargate partners",
      "utility_or_service_provider": "Emirates Water and Electricity Company (EWEC) (grid-operator context)",
      "utility_type": "regional/national electricity system operator",
      "transmission_interconnection_provider": "UAE transmission / local distribution connection process",
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "Announced/under development; no public site-specific connection case found",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": "2026-09-27",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 4,
        "unpopulated_detailed_fields": 12,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "transmission_interconnection_provider",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-78e7d8474fbdf968",
      "epoch_name": "OpenAI Stargate Wisconsin",
      "country": "United States",
      "state_province": "WI",
      "address": null,
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "MISO",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.misoenergy.org/api/giqueue/getprojects",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State WI is assigned to the MISO queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 39.8,
      "lon": -98.6,
      "precision": "country centroid",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_SPECIFIC_GRID_CONNECTION_EVIDENCE",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "OpenAI / Oracle; Vantage developer/operator",
      "utility_or_service_provider": "We Energies (WEC Energy Group)",
      "utility_type": "electric utility / very-large-customer service",
      "transmission_interconnection_provider": "American Transmission Company (ATC)",
      "substation": "ATC substations serving site (names not publicly published in reviewed source)",
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": 1300,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": 3500,
      "public_record_status": "Grid connection in progress; MISO in-service date moved to 2027-12-01; ATC awarded substations serving the site",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": "2027-12-01",
      "connection_research_notes": "1.3 GW is the connection sought from We Energies; 3.5 GW is long-term site potential. These values are not equated with current IT load or a PJM/MISO queue row.",
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 8,
        "unpopulated_detailed_fields": 8,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider",
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "service_capacity_mw",
          "site_planned_mw",
          "target_in_service_date",
          "connection_research_notes"
        ],
        "unpopulated_fields": [
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "request_or_study_date",
          "service_or_approval_date"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-d2da66ea035880ce",
      "epoch_name": "QTS Cedar Rapids",
      "country": "United States",
      "state_province": "IA",
      "address": "6200 76th Ave SW, Fairfax, IA 52228",
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "MISO",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://www.misoenergy.org/api/giqueue/getprojects",
      "source_type": "RTO/ISO official",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State IA is assigned to the MISO queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 42.1,
      "lon": -93.5,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 2,
      "site_level_evidence": [
        {
          "type": "site_specific_utility_relationship",
          "authority": "Alliant Energy",
          "record_name": "QTS Cedar Rapids / Big Cedar campus",
          "source_url": "https://www.alliantenergy.com/news/news-center/2025/02/021225-qtsannouncementcr",
          "source_kind": "official utility disclosure",
          "confidence": "high",
          "basis": "Alliant officially confirmed QTS's Cedar Rapids data-center campus on 612 acres of the Big Cedar Industrial Center."
        },
        {
          "type": "site_specific_load_request",
          "authority": "MISO",
          "record_name": "SNA LLC Cedar Rapids new-load announcement",
          "capacity_mw": 616,
          "source_url": "https://cdn.misoenergy.org/NEW%20LOAD%20ANNOUNCEMENTS%20IN%20MISO%20REGIONS%2012062024684954.pdf",
          "source_kind": "official MISO new-load announcement",
          "confidence": "medium",
          "basis": "MISO public new-load announcement lists a 616 MW Cedar Rapids request under shell company SNA LLC; secondary facility research associates this request with the QTS phase, so identity is retained as medium rather than promoted to a direct queue ID."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "QTS Cedar Rapids",
      "utility_or_service_provider": "Alliant Energy",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    },
    {
      "epoch_id": "EPOCH-4b4d686b6c457a68",
      "epoch_name": "QTS Eagle Mountain",
      "country": "United States",
      "state_province": "UT",
      "address": "652 E Hyperscale Way, Eagle Mountain, UT 84013",
      "current_it_power_mw": 0,
      "current_h100_equivalents": 0,
      "grid_or_queue_jurisdiction": "WECC / Utah serving utility",
      "scope": "within_registry_geography",
      "status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "site_specific_queue_id": null,
      "site_specific_queue_name": null,
      "site_specific_capacity_mw": null,
      "primary_source_url": "https://wattstreet.net/state/ut/",
      "source_type": "state queue coverage index",
      "source_date": "2026-09-26",
      "next_research_sources": "GridTracker; Interconnection.fyi; Watt Street; FERC eLibrary; SueDataCenters / Compute Atlas; DataCenter.fyi",
      "match_basis": "State UT is assigned to the WECC / Utah serving utility queue/connection jurisdiction; this establishes coverage, not a site-specific queue ID.",
      "confidence": "jurisdiction",
      "next_action": "Search the named queue family, then local utility/municipal/co-op records and state PUC/PSC filings for the site-specific request/connection record.",
      "lat": 39.3,
      "lon": -111.7,
      "precision": "state centroid derived from public address",
      "site_level_evidence_status": "evidence_found",
      "site_level_evidence_count": 1,
      "site_level_evidence": [
        {
          "epoch_id": "EPOCH-4b4d686b6c457a68",
          "type": "site_specific_utility_relationship",
          "authority": "Rocky Mountain Power",
          "record_name": "QTS Eagle Mountain serving-utility relationship",
          "source_url": "https://registry.deploy.report/datacenters/facilities/qts-eagle-mountain-eagle-mountain-ut",
          "source_kind": "secondary sourced facility registry",
          "confidence": "medium",
          "basis": "DEPLOY identifies Rocky Mountain Power as the serving utility for QTS's Eagle Mountain facility in Utah. The QTS facility record independently states it is working directly with local utilities on power needs and that QTS will pay for project energy infrastructure."
        }
      ],
      "existing_queue_crosswalk": null,
      "connection_match_status": "SITE_LEVEL_EVIDENCE_RETAINED",
      "research_capture_date": "2026-09-26",
      "customer_or_developer": "Meta #speculative",
      "utility_or_service_provider": "Rocky Mountain Power",
      "utility_type": null,
      "transmission_interconnection_provider": null,
      "substation": null,
      "transmission_line": null,
      "site_specific_queue_capacity_mw": null,
      "service_capacity_mw": null,
      "approved_capacity_mw": null,
      "contract_ceiling_mw": null,
      "site_planned_mw": null,
      "public_record_status": "queue_jurisdiction_mapped_site_id_not_yet_verified",
      "request_or_study_date": null,
      "service_or_approval_date": null,
      "target_in_service_date": null,
      "connection_research_notes": null,
      "alternative_candidates": [],
      "connection_field_accounting": {
        "total_detailed_fields": 16,
        "populated_detailed_fields": 1,
        "unpopulated_detailed_fields": 15,
        "accounted_for_fields": 16,
        "accounted_for_pct": 100,
        "missing_field_disposition": "NOT_PUBLICLY_RETAINED",
        "populated_fields": [
          "utility_or_service_provider"
        ],
        "unpopulated_fields": [
          "utility_type",
          "transmission_interconnection_provider",
          "substation",
          "transmission_line",
          "site_specific_queue_id",
          "site_specific_queue_name",
          "site_specific_queue_capacity_mw",
          "service_capacity_mw",
          "approved_capacity_mw",
          "contract_ceiling_mw",
          "site_planned_mw",
          "request_or_study_date",
          "service_or_approval_date",
          "target_in_service_date",
          "connection_research_notes"
        ]
      }
    }
  ],
  "accounting_note": "100% accounted-for detailed connection fields means every defined field has either a retained public value or an explicit NOT_PUBLICLY_RETAINED disposition. It does not mean every field is publicly populated.",
  "field_catalog": {
    "utility_or_service_provider": {
      "label": "Utility / service provider",
      "populated_records": 75,
      "coverage_pct": 80.6,
      "definition": "Published/retained value when present; otherwise explicitly NOT_PUBLICLY_RETAINED in the public interface."
    },
    "utility_type": {
      "label": "Utility type",
      "populated_records": 16,
      "coverage_pct": 17.2,
      "definition": "Published/retained value when present; otherwise explicitly NOT_PUBLICLY_RETAINED in the public interface."
    },
    "transmission_interconnection_provider": {
      "label": "Transmission interconnection provider",
      "populated_records": 24,
      "coverage_pct": 25.8,
      "definition": "Published/retained value when present; otherwise explicitly NOT_PUBLICLY_RETAINED in the public interface."
    },
    "substation": {
      "label": "Substation / POI",
      "populated_records": 2,
      "coverage_pct": 2.2,
      "definition": "Published/retained value when present; otherwise explicitly NOT_PUBLICLY_RETAINED in the public interface."
    },
    "transmission_line": {
      "label": "Transmission line",
      "populated_records": 0,
      "coverage_pct": 0,
      "definition": "Published/retained value when present; otherwise explicitly NOT_PUBLICLY_RETAINED in the public interface."
    },
    "site_specific_queue_id": {
      "label": "Site-specific queue ID",
      "populated_records": 2,
      "coverage_pct": 2.2,
      "definition": "Published/retained value when present; otherwise explicitly NOT_PUBLICLY_RETAINED in the public interface."
    },
    "site_specific_queue_name": {
      "label": "Queue / project name",
      "populated_records": 5,
      "coverage_pct": 5.4,
      "definition": "Published/retained value when present; otherwise explicitly NOT_PUBLICLY_RETAINED in the public interface."
    },
    "site_specific_queue_capacity_mw": {
      "label": "Queue capacity (MW)",
      "populated_records": 4,
      "coverage_pct": 4.3,
      "definition": "Published/retained value when present; otherwise explicitly NOT_PUBLICLY_RETAINED in the public interface."
    },
    "service_capacity_mw": {
      "label": "Service capacity (MW)",
      "populated_records": 4,
      "coverage_pct": 4.3,
      "definition": "Published/retained value when present; otherwise explicitly NOT_PUBLICLY_RETAINED in the public interface."
    },
    "approved_capacity_mw": {
      "label": "Approved capacity (MW)",
      "populated_records": 2,
      "coverage_pct": 2.2,
      "definition": "Published/retained value when present; otherwise explicitly NOT_PUBLICLY_RETAINED in the public interface."
    },
    "contract_ceiling_mw": {
      "label": "Contract ceiling (MW)",
      "populated_records": 1,
      "coverage_pct": 1.1,
      "definition": "Published/retained value when present; otherwise explicitly NOT_PUBLICLY_RETAINED in the public interface."
    },
    "site_planned_mw": {
      "label": "Site planned MW",
      "populated_records": 32,
      "coverage_pct": 34.4,
      "definition": "Published/retained value when present; otherwise explicitly NOT_PUBLICLY_RETAINED in the public interface."
    },
    "request_or_study_date": {
      "label": "Request / study date",
      "populated_records": 5,
      "coverage_pct": 5.4,
      "definition": "Published/retained value when present; otherwise explicitly NOT_PUBLICLY_RETAINED in the public interface."
    },
    "service_or_approval_date": {
      "label": "Service / approval date",
      "populated_records": 5,
      "coverage_pct": 5.4,
      "definition": "Published/retained value when present; otherwise explicitly NOT_PUBLICLY_RETAINED in the public interface."
    },
    "target_in_service_date": {
      "label": "Target in-service date",
      "populated_records": 5,
      "coverage_pct": 5.4,
      "definition": "Published/retained value when present; otherwise explicitly NOT_PUBLICLY_RETAINED in the public interface."
    },
    "connection_research_notes": {
      "label": "Connection research notes",
      "populated_records": 24,
      "coverage_pct": 25.8,
      "definition": "Published/retained value when present; otherwise explicitly NOT_PUBLICLY_RETAINED in the public interface."
    }
  },
  "summary": {
    "total_sites": 93,
    "sites_with_jurisdiction": 93,
    "sites_with_connection_status": 93,
    "sites_with_provider": 75,
    "sites_with_site_evidence": 93,
    "site_specific_queue_ids": 2,
    "detailed_field_count": 16,
    "detailed_fields_total": 1488,
    "detailed_fields_populated": 206,
    "detailed_fields_accounted": 1488,
    "detailed_fields_accounted_pct": 100,
    "detailed_field_population_pct": 13.8,
    "field_population_counts": {
      "utility_or_service_provider": 75,
      "utility_type": 16,
      "transmission_interconnection_provider": 24,
      "substation": 2,
      "transmission_line": 0,
      "site_specific_queue_id": 2,
      "site_specific_queue_name": 5,
      "site_specific_queue_capacity_mw": 4,
      "service_capacity_mw": 4,
      "approved_capacity_mw": 2,
      "contract_ceiling_mw": 1,
      "site_planned_mw": 32,
      "request_or_study_date": 5,
      "service_or_approval_date": 5,
      "target_in_service_date": 5,
      "connection_research_notes": 24
    },
    "record_published_detail_field_distribution": {
      "1": 55,
      "2": 16,
      "3": 8,
      "4": 7,
      "5": 3,
      "7": 1,
      "8": 1,
      "9": 1,
      "10": 1
    }
  }
}